From
Glenda Peterson
Title
Amendment/Change order No. 3 with North Rock Construction, LLC in the amount of $47,889.47 for the rehabilitation of two bridges over Fish Creek located at South Great Southwest Parkway over Fish Creek and South Robinson Road over Fish Creek
Presenter
Gabriel Johnson, Public Works Director
Recommended Action
Approve
Analysis
On September 5, 2018 the City awarded a construction contract to North Rock Construction, LLC in the amount of $673,836, with a contingency of $33,692, for a total project cost of $707,528. This project provided for the rehabilitation of two bridges over Fish Creek located at South Great Southwest Parkway over Fish Creek and South Robinson Road over Fish Creek.
Proposed Amendment/Change order No. 3 in the amount of $47,889.47 provided for final quantities reconciliation due upon project completion.
Amendment/Change order No. 2 in the amount of $9,547.20 provided for additional traffic rail, concrete flume, and removal of existing sidewalk at the South Robinson Road over Fish Creek location.
Amendment/Change order No. 1 in the amount of $19,661.60 provided for additional concrete work needed for the South Robinson Road over Fish Creek location.
Project completion date was May 3, 2019.
State statutes require City Council approval of a change order when the cumulative cost of this change order exceeds $50,000. Also, the City, as an owner, reserves the right to increase the amount of the work to be performed in a given construction contract by an amount not to exceed twenty-five (25%) percent of the original bid. With approval of the current amendment/change order, the percent of original bid will be 11.44%. The cumulative amounts of Amendment/Change order No. 1 ($19,661.60), Amendment/Change order No. 2 ($9,547.20) and current Amendment/Change order No. 3 ($43,406.27) is $72,615.07 which required Council approval.
Financial Consideration
Funding for Amendment/Change order No. 3 with North Rock Constr...