Legislation Details

File #: 19-9461    Version: 1 Name: Professional Engineering Services Contract with Halff Associates, Inc. for the design and construction management of the Johnson Creek Channel Wall and Floor Repairs in the amount of $140,105.00 plus a 5% contingency of $7,005.00 comes to a total projecte
Type: Agenda Item Status: Consent Agenda
File created: 10/16/2019 In control: Engineering
On agenda: 11/5/2019 Final action: 11/5/2019
Title: Professional Engineering Services Contract with Halff Associates, Inc. for the design and construction management of the Johnson Creek Channel Wall and Floor Repairs in the amount of $140,105.00 plus a 5% contingency of $7,005.00, for a total projected cost of $147,110
Attachments: 1. 19-9461 Johnson Crk.pdf, 2. Johnson Creek Floor and Wall Repair Locations

From

Stephanie Griffin

 

Title

Professional Engineering Services Contract with Halff Associates, Inc. for the design and construction management of the Johnson Creek Channel Wall and Floor Repairs in the amount of $140,105.00 plus a 5% contingency of $7,005.00, for a total projected cost of $147,110

Presenter

Gabe Johnson, Director of Public Works and Stephanie Griffin, Stormwater Utility Manager/Floodplain Administrator

 

Recommended Action

Approve

 

Analysis

September and October 2018 flood events. The design capacity of the overflow channel was exceeded and the wall failed when the floodwaters overtopped it. The channel flood has multiple locations that experienced significant erosion.

Chapter 252, Section 22 of the Local Government Code allows for the exemption to competitive bidding when the expenditure is for Professional Services such as engineering services. Halff Associates, Inc was selected as the most qualified professional due to their familiarity with similar projects and their past record of performance on City projects.

 

Halff has provided a proposal to design the necessary repairs for the channel wall and channel floor. The scope of work includes the following tasks:

•                     Task A: Field Survey

•                     Task B: Data Collection and Project Planning

•                     Task C: Preliminary Design (30%)

•                     Task D: Preliminary Design (70%)

•                     Task E: Final Design (95-100%)

•                     Task F: Bidding Services

•                     Task G: Construction Phase Services

 

Financial Consideration

Funding for a Professional Engineering Services Contract with Halff Associates, Inc. for the design and construction management of the Johnson Creek Channel Wall and Floor Repairs in the amount of $140,105.00 plus a 5% contingency of $7,005.00, for a total projected cost of $147,110, is available is the Storm Drainage Capital Projects Fund (401592) WO #02004903 (Johnson Creek Channel Repairs)