File #: 19-9549    Version: 1 Name: Change Order/Amendment No. 7 w/Teague, Nall and Perkins, Inc. for Seeton Road
Type: Agenda Item Status: Consent Agenda
File created: 11/8/2019 In control: Engineering
On agenda: 11/19/2019 Final action: 11/19/2019
Title: Change Order/Amendment No.7 in the amount of $89,488 with Teague, Nall and Perkins, Inc. (TNP) for Seeton Road paving, drainage and waterline design between Grand Peninsula Parkway and Day Miar Road
Attachments: 1. 620.64 Seeton.pdf
From
George Fanous

Title
Change Order/Amendment No.7 in the amount of $89,488 with Teague, Nall and Perkins, Inc. (TNP) for Seeton Road paving, drainage and waterline design between Grand Peninsula Parkway and Day Miar Road

Presenter
Walter Shumac, Director of Transportation, and Romin Khavari, City Engineer

Recommended Action
Approve

Analysis
On December 15, 2015 the City of Grand Prairie awarded a Professional Engineering Services contract with Teague, Nall and Perkins, Inc. for paving, drainage and waterline design of Seeton Road between Grand Peninsula Parkway and Day Miar Road in the amount of $424,800

Proposed Change order/ Amendment No.7 in the amount of $89,488 provides for additional design services related to plan revisions resulting from new developments occurring along the project Corridor, construction sequencing revisions, updating traffic counts in the project area, coordination with City of Mansfield and with the United States Army Corps of Engineers, updating plan details and contract documents to incorporate City’s current standards, design revisions to water and sewer plans and additional two years of time extension to the current design contract. The revised contract termination date will be 12/31/2021.

Change Order /Amendment No.1 in the amount of $13,200 provided for Design of approximately 950 linear feet of wastewater main in Seeton Road from Lake Way Estates Northern Limits to Spring Creek Circle.

Change Order/Amendment No.2 in the amount of $17, 800 provided for the design and plan preparation of 980 Linear feet of wastewater main in Seeton road and the decommissioning of the Lakeview West lift Station; it also provided for the review and comment on the proposed wastewater and overall design of the Lake way Estates Development along Seeton Road.

Change Order/Amendment No.3 in the amount of $16,500 provided for the Coordination and Permitting with the United States Army Corps of Engineers (USACE) for impacts to Jurisdi...