Legislation Details

File #: 19-9574    Version: 1 Name: Change Order No. 2 with SYB Construction Company, Inc for Drainage Improvements 1800 2200 North Carrier Parkway in the in the net amount of $58,786.00.
Type: Agenda Item Status: Consent Agenda
File created: 11/20/2019 In control: Engineering
On agenda: 12/17/2019 Final action: 12/17/2019
Title: Change Order No. 2 with SYB Construction Company, Inc for Drainage Improvements 1800-2200 North Carrier Parkway in the in the net amount of $58,786.00.
Attachments: 1. 619.56.pdf
From
max

Title
Change Order No. 2 with SYB Construction Company, Inc for Drainage Improvements 1800-2200 North Carrier Parkway in the in the net amount of $58,786.00.

Presenter
Gabe Johnson, Director of Public Works and Romin Khavari, City Engineer

Recommended Action
Approve

Analysis
On Tuesday, June 18, 2019 the City of Grand Prairie awarded a construction contract to SYB Construction Company, Inc. in the amount of $898,656.84 for Drainage Improvements 1800-2200 North Carrier Parkway.

This proposed change order No. 2 will increase the amount of sidewalk replacement authorized in change order #1 by 11 square yards to allow the installation of the box culvert line A, increase the amount of pavement replacement by 325 square yards to provide additional compensation for needed pavement replacement and downsizing the proposed storm drain laterals to clear the discovered GPISD and telemarket company fiber optics lines. This change order includes removal of 16 linear feet of installed 30” Class IV RCP, decrease of contract quantities of 25 linear feet for 3’ by 2’ RCB conduit, of 28 linear feet for 30” Class IV RCP, of 50 linear feet for 30” Class III RCP, of 21 linear feet for 21” Class IV RCP and addition of 50 linear feet of 18” Class III RCP, 47 linear feet of 18” Class IV RCP and 45 linear feet of 12” Class IV RCP for storm drain lateral downsizing to clear the existing fiber optic lines. New items for connections of the downsized storm drain conduits are also provided in this change order.

Change order #1 was approved on October 28, 2019 in the amount of $15,097.00 for sidewalk replacement, removal of two large trees, 64 linear foot replacement of the existing 24” Class III RCP for storm drain line E and connection of the storm drain laterals to two existing curb inlets.

Construction completion of the project is to be extended to March 24, 2020.

Financial Consideration
State statutes require City Council approval of a change order when the cumul...

Click here for full text