From
max
Title
Ordinance amending the FY 2019/2020 Capital Improvements Projects Budget; Change Order/Amendment No. 1 with Hill & Wilkinson General Contractors in the amount of $6,215,173 for the balance of construction cost for Phase Two of the Civic Campus Master Plan project; 5% contingency in the amount of $310,759; $1,200,000 allowance for owner-provided furniture, fixtures and equipment (FF&E); $95,000 allowance for door access and security systems; $95,000 allowance for IT/data design and installation; $200,000 allowance for audio/visual (AV) equipment; $25,000 allowance for construction testing; plus a $125,000 allowance for Oncor Electric power line relocation for a total funding request in the amount of $8,265,932.
Presenter
Andy Henning, Senior Building and Construction Projects Manager
Recommended Action
Approve
Analysis
On June 4, 2019 the City Council awarded the Construction Manager at Risk (CMAR) contract to Hill & Wilkinson General Contractors (19-9024) for pre-construction services in the amount of zero dollars ($0). This award provided for CMAR services including development of project estimates, preliminary construction schedules, value engineering proposals and constructability review during the Design Phase.
The current Change Order/Amendment No. 1 in the amount of $6,215,173 represents the Guaranteed Maximum Price (GMP) for the scope of work currently defined in the Rouch Architects Construction Documents package as competitively bid by Subcontractors to Hill & Wilkinson. 5% contingency ($310,759); allowance for FF&E ($1,200,000); allowance for IT/data design and installation ($95,000); allowance for A/V equipment ($200,000); allowance for door access and security systems ($95,000); allowance for Oncor Electric power line relocation ($125,000); plus an allowance for construction testing ($25,000).
Costs above and beyond the Hill & Wilkinson portion of the project addressed in this Change Order Amendment include previously ap...
Click here for full text