Steve Plumer, Sr Park Planning Project Manager
Title
Change order #4 for PlayGrand Adventures Phase 1 with Hill and Wilkinson Inc in the amount of $116,180.01 for additional drainage, masonry, wood fiber and sod, retaining wall footing revisions, PIP rubber surfacing, triangular column stone addition and credit for deletion of work.
Presenter
Cheryl De Leon, Director of Parks, Arts and Recreation
Recommended Action
Approve
Analysis
On June 17, 2018, the City Council awarded the Construction Manager at Risk (CMAR) contract to Hill & Wilkinson, Inc. for Pre-Construction services in the amount of $3,000. This award provided the CMAR services including development of project estimates, preliminary construction schedule, value engineering and constructability review during the design phase.
Change Order No. 1 in the amount of $5,549,995 was approved by City Council on November 6, 2018 for the GMP contract for construction.
Change Order No. 2, in the amount of $74,493.35 was approved by City Council on May 7, 2019 for soil conditioning, additional site work, revisions to a concrete retaining wall, and various credits for deletion of work and included a credit for sidewalk, landscape and irrigation at the intersection of Warrior Trail and EPIC Place.
Change Order No. 3, in the amount of $25,541.95 was approved by City Council on September 9, 2019 for masonry, concrete foundations, electrical & lighting, drainage, site work, and various credits for deletion of work.
Change Order No 4. in the amount of $116,180.01 is for additional drainage, masonry, wood fiber and sod, retaining wall footing revisions, PIP rubber surfacing, triangular column stone addition and credit for deletion of work.
All items will be incorporated into the current Hill & Wilkinson, Inc. contract for a revised total contract amount of $5,766,210.31. With approval of this agenda item, the original contract value will have been increased by 3.7% in total, which is within the 25% ...