Fire Station 4+6 Final Change Order/Amendment No. 4 with Key Construction in the amount of $62,885.89 for Proposed Change Orders (PCOs) #005, #006 and #007 resulting from necessary work to coordinate, complete and closeout the overall fire station project
Presenter
Andy Henning, Senior Building and Construction Projects Manager
Recommended Action
Approve
Analysis
On June 5, 2018 the City Council awarded the Construction Manager at Risk (CMAR) contract to Key Construction for pre-construction services in the amount of $15,000. This award provided for CMAR services including development of project estimates, preliminary construction schedules, value engineering proposals and constructability review during the Design Phase.
The current Change Order/Amendment No. 4 in the amount of $62,885.89 is divided as follows:
$10,936.00 for PCO #005 consisting of added power and cord reels, HVAC changes associated with ASI 04, corresponding electrical changes required, site civil changes, void form encasement and miscellaneous project changes resulting in money-saving credits to the project (9 in total)
$17,242.58 for PCO #006 consisting of a new exhaust fan, power/data adjustments and additions, added miscellaneous steel supports at masonry and canopy areas, safety strip lighting at overhead door exits and credit for project buyout savings from the construction manager
$34,707.31 for PCO #007 consisting of high early strength concrete for inspection schedule acceleration, building mounted Fire Department Connection (FDC), workout room mirror reduction credit, credit for rubber base manufacturer change, exterior guardrails at back vehicular entry gate track opening and added concrete drainage flume to avoid water ponding and runoff to residential neighbors
Change Order/Amendment No. 1 in the amount of $4,400,000 was approved by City Council on August 7, 2018 (18-8082) for the Guaranteed Maximum Price (GMP) for the addition to Fire Station 6 sco...