Change Order/Amendment No. 5 with Modern Contractors for Fleet Services Center Additions and Renovations (Phase Two) in the amount of $176,052.11 for plumbing additions and deletions, adjustment of construction manager contract costs, electrical work for EV charging stations, structural additions, expansion of new concrete parking/sidewalk surface, extended irrigation, mechanical/electrical coordination, added door hardware, fire extinguishers, soil chemical injection, protective bollards and millwork revisions.
Presenter
Andy Henning, Senior Construction and Projects Manager
Recommended Action
Approve
Analysis
On August 7, 2018 (18-8084) the City Council awarded the Construction Manager at Risk (CMAR) contract to Modern Contractors for pre-construction services in the amount of $1,000. This award provided for CMAR services including development of project estimates, preliminary construction schedules, value engineering proposals and constructability review during the Design Phase.
Current Change Order/Amendment No. 5 in the amount of $176,052.11 is divided as follows:
$4,907.09 for change from 1 ½” to 2 ½” double check valve with freeze protection cavity wall
-$7,785.00 credit for removal of oil/water separator
$9,961.24 for construction manager overhead/profit percentages not included in prior change orders
$7,359.61 for electric vehicle charging equipment and final electrical connections
$23,956.72 for structural additions for hose reels, ceiling fan support and guard rails
$545.57 for roof drain washout pit
$63,324.22 for expansion of new concrete parking at northeast corner of site
$2,961.95 for added irrigation to support new grass area installed
$2,684.17 for ground-fault circuit interrupter (GFCI) breakers for new appliances per City inspector
$702.90 for mechanical ductwork modifications at storage mezzanine to cap previous routing
$792.77 for added door closer hardware
$546.20 for four (4) fire extinguishers per Fire Marshal...