From
Mark Dempsey
Title
Compromise, Settlement and Release Agreement with HKS Architects regarding Epic Waters and The Epic
Presenter
Andy Henning - Senior Building and Construction Projects Manager
Recommended Action
Approve
Analysis
In November of 2014, the City entered into a professional services agreement with HKS for architectural services in connection with the The Epic and Epic Waters. The City determined there were design deficiencies associated with work performed by HKS under certain change orders it submitted under the contract. All of the change orders were paid by the City. There is one outstanding change order request filed by HKS in the amount of $46,875. In settlement of the dispute, HKS has agreed to withdraw the $46,875 change order request, and pay the City $31,085.50 as compensation for the alleged deficiencies.
Financial Consideration
none