From
Steve Plumer, Sr. Park Planner
Title
Change Order/Amendment No. 7 for PlayGrand Adventures Phase 1 with Hill & Wilkinson., in the amount of $81,557.35 for multiple items including irrigation power relocation, concrete, earthwork, landscape and irrigation additions and an allowance for haul off of spoils due to compliance with Oncor Electric easement requirements as related to the parking expansion
Presenter
Duane Strawn, Director of Parks, Arts and Recreation
Recommended Action
Approve
Analysis
On June 17, 2018, the City Council awarded the Construction Manager at Risk (CMAR) contract to Hill & Wilkinson, Inc. for Pre-Construction services in the amount of $3,000. This award provided the CMAR services including development of project estimates, preliminary construction schedule, value engineering and constructability review during the design phase.
Change Order/Amendment No. 1, in the amount of $5,549,995 was approved by City Council on November 6, 2018 for the GMP contract for construction.
Change Order/Amendment No. 2, in the amount of $74,493.35 was approved by City Council on May 7, 2019 for soil conditioning, additional site work, revisions to a concrete retaining wall, and various credits for deletion of work and included a credit for sidewalk, landscape and irrigation at the intersection of Warrior Trail and EPIC Place.
Change Order/Amendment No 3, in the amount of $25,541.95 was approved by City Council on September 9, 2019 for masonry, concrete foundations, electrical & lighting, drainage, site work, and various credits for deletion of work.
Change Order/Amendment No. 4, in the amount of $116,180.01 was approved by City Council on December 17, 2019 for additional drainage, masonry, wood fiber and sod, retaining wall footing revisions, PIP rubber surfacing, triangular column stone addition and credit for deletion of work.
Change Order/Amendment No. 5, in the amount of $392,694.05 was approved by City Council on February 4, 2020 for...