Legislation Details

File #: 20-10119    Version: 1 Name: Change Order #4 to Construction contract with Axis Contracting, Inc.for Intersection Improvements at three locations
Type: Ordinance Status: Adopted
File created: 6/26/2020 In control: Engineering
On agenda: 7/14/2020 Final action: 7/14/2020
Title: Change Order/Amendment No. 4 in the net amount of $7,827 with Axis Contracting, Inc. for Intersection Improvements at three locations
Attachments: 1. 620.70.pdf

From

max

 

Title

Change Order/Amendment No. 4 in the net amount of $7,827 with Axis Contracting, Inc. for Intersection Improvements at three locations

 

Presenter

Walter Shumac, Director of Transportation, and Romin Khavari, City Engineer

 

Recommended Action

Approve

 

Analysis

On December 17, 2019 City Council Approved a construction Contract with Axis Contracting, Inc. in the amount of $1,252,354 for Intersection Improvements at three locations; Material testing with Team Consultants in the amount of $28,275; 5% contingency in the amount of $62,618; In-house labor distribution in the amount of $62,618 for a total project cost of $1,405,865.                                          

 

This project provides for paving, sidewalks, Barrier free ramps, traffic signals and drainage improvements at Lone Star Parkway/S. Belt Line Road, Great Southwest Parkway/Lake Ridge Parkway, and Jefferson Street/ South Carrier Parkway intersections.

 

Proposed Change order/Amendment No. 4 provides for Traffic signal modifications at south Carrier Parkway/Jefferson Street intersection for a total increase of $11,142 and a total decrease of $3,315 for a net total increase of $7,827.   

 

Change order/Amendment No. 3 in the amount of $41,580 provided for Storm drain modifications due to conflicts at South Carrier Pkwy/ Jefferson St. intersections.

 

Change order/Amendment No. 2 in the amount of $4,275 provided for Electrical Wire adjustments at Great Southwest Pkwy/ Lakeridge Pkwy Intersection.

 

Change order/Amendment No. 1 was voided under C.O 3 due to a technical error.

 

Completion Date Remains December 7, 2020

 

Financial Consideration

Funding for change order/amendment #4, in the total amount of $7,827, is available in the Street Capital Projects Fund (400192) WO #02007003 (FY20 Intersection Improvements)