Change Order/Amendment No. 4 in the net amount of $7,827 with Axis Contracting, Inc. for Intersection Improvements at three locations
Presenter
Walter Shumac, Director of Transportation, and Romin Khavari, City Engineer
Recommended Action
Approve
Analysis
On December 17, 2019 City Council Approved a construction Contract with Axis Contracting, Inc. in the amount of $1,252,354 for Intersection Improvements at three locations; Material testing with Team Consultants in the amount of $28,275; 5% contingency in the amount of $62,618; In-house labor distribution in the amount of $62,618 for a total project cost of $1,405,865.
This project provides for paving, sidewalks, Barrier free ramps, traffic signals and drainage improvements at Lone Star Parkway/S. Belt Line Road, Great Southwest Parkway/Lake Ridge Parkway, and Jefferson Street/ South Carrier Parkway intersections.
Proposed Change order/Amendment No. 4 provides for Traffic signal modifications at south Carrier Parkway/Jefferson Street intersection for a total increase of $11,142 and a total decrease of $3,315 for a net total increase of $7,827.
Change order/Amendment No. 3 in the amount of $41,580 provided for Storm drain modifications due to conflicts at South Carrier Pkwy/ Jefferson St. intersections.
Change order/Amendment No. 2 in the amount of $4,275 provided for Electrical Wire adjustments at Great Southwest Pkwy/ Lakeridge Pkwy Intersection.
Change order/Amendment No. 1 was voided under C.O 3 due to a technical error.
Completion Date Remains December 7, 2020
Financial Consideration
Funding for change order/amendment #4, in the total amount of $7,827, is available in the Street Capital Projects Fund (400192) WO #02007003 (FY20 Intersection Improvements)