File #: 20-10142    Version: 1 Name: Change Order/Amendment #1 for Professional Engineering Services contract with Freese and Nichols, Inc. for the Robinson Road Pump Station and Elevated Storage Tank
Type: Ordinance Status: Adopted
File created: 7/2/2020 In control: Engineering
On agenda: 7/14/2020 Final action: 7/14/2020
Title: Change Order/Amendment #1 to the Professional Engineering Services contract with Freese and Nichols, Inc. for the Robinson Road Pump Station and Elevated Storage Tank in the amount of $84,400
Attachments: 1. 20-10142 Robinson ESt.pdf
From
max

Title
Change Order/Amendment #1 to the Professional Engineering Services contract with Freese and Nichols, Inc. for the Robinson Road Pump Station and Elevated Storage Tank in the amount of $84,400

Presenter
Gabe Johnson, Director of Public Works

Recommended Action
Approve

Analysis
The Robinson Road Pump Station and Elevated Storage Tank was identified as part of the FY 19 Capital Projects Budget and Capital Projects Plan for proposed water projects. A contract was approved by City Council (19-8529) on January 8, 2019 in the amount of $1,695,000. The design included the following:

- Robinson Road 12 MGD Pump Station
Design of Pump Station and appurtenances to house four (4) new horizontal split case pumps and motors to deliver a firm capacity of 12 MGD and associated yard piping required to connect the proposed Pump Station to the existing system
Bid Phase Services
General Representation Construction Phase Services

- Robinson Road 2 MG Composite Elevated Storage Tank
Design of Composite Elevated Storage Tank and appurtenances
Chemical Storage Tanks and Pads for Residual Boosting
Design of an Active Mixing System

- Demolition of Site Facilities
Existing Fire Station to include asbestos sampling
Existing elevated Storage Tank to include Heavy Metals Paint sampling
Existing Fire Tower and associated training equipment
Existing Elevated Storage tank as part of elevated Storage Tank construction package

- Sub-consultant work for lead and asbestos sampling, survey, drilling and testing.

The current Change Order/Amendment #1 in the amount of $84,400 will include:

-Sanitary Sewer Replacement (Design, Bid and Construction Services) up to 800 LF of 8" SS including additional survey south of existing Fire Station #3 property along Robinson Rd.
-Auxiliary Parking Lot (Design Services Only) of no more than 9,500 sf including additional drainage coordination and pavement plan
- Valve Vaults (Design, Bid and Construction Service...