Change Order/Amendment No. 4 with Hill & Wilkinson General Contractors for City Hall Municipal Campus Phase Two construction work in the amount of $103,689.52 for millwork changes, structural repair, concrete ramp work, protective wall covering, additional drainage, structural steel modifications, masonry infill, interior finish revisions, roller shades, breakroom equipment changes and building exterior finish adjustments
Presenter
Andy Henning, Senior Building and Construction Projects Manager
Recommended Action
Approve
Analysis
On June 4, 2019 the City Council awarded the Construction Manager at Risk (CMAR) contract to Hill & Wilkinson General Contractors (19-9024) for pre-construction services in the amount of zero dollars ($0). This award provided for CMAR services including development of project estimates, preliminary construction schedules, value engineering proposals and constructability review during the Design Phase.
Current Change Order/Amendment No. 4 in the amount of $103,689.52 is divided as follows:
$9,603.60 for millwork changes to lobby drawing review counter including added structural steel
$7,361.04 for repair of an existing concrete grade beam that was discovered to be damaged
$8,922.02 for concrete ramp work due to uncovered floor elevation conflict at southwest connector
$4,545.99 for protective wall covering in conference rooms to prevent wall damage from chairs
$1,917.99 for a curb drain to coordinate with existing grades and new concrete ramp construction
$7,537.97 for added structural steel at east façade to address existing conditions lacking support
$3,297.86 for concrete masonry block infill at hidden opening condition uncovered
$70,837.11 for reinstatement of interior finish materials previously removed from lobby design
$2,089.70 for additional manually operated roller shades at south-facing lobby huddle rooms
$2,406.92 credit for deletion of specialty breakroom equipment not required
$10,0...