Legislation Details

File #: 20-10476    Version: 1 Name: Change Order/Amendment No. 5 with Hill & Wilkinson General Contractors for City Hall Municipal Campus Phase Two construction work in the amount of $98,214.32 for plumbing work, landscaping additions, COVID 19 costs, added painting scope, repair of existin
Type: Agenda Item Status: Consent Agenda
File created: 10/16/2020 In control: Engineering
On agenda: 11/3/2020 Final action: 11/3/2020
Title: Change Order/Amendment No. 5 with Hill & Wilkinson General Contractors for City Hall Municipal Campus Phase Two construction work in the amount of $98,214.32 for plumbing work, landscaping additions, COVID-19 costs, added painting scope, repair of existing conditions, removal of the temporary construction yard and adjustments based on code requirements.
Attachments: 1. WO 620.26.pdf
From
max

Title
Change Order/Amendment No. 5 with Hill & Wilkinson General Contractors for City Hall Municipal Campus Phase Two construction work in the amount of $98,214.32 for plumbing work, landscaping additions, COVID-19 costs, added painting scope, repair of existing conditions, removal of the temporary construction yard and adjustments based on code requirements.

Presenter
Andy Henning, Senior Building and Construction Projects Manager

Recommended Action
Approve

Analysis
On June 4, 2019 the City Council awarded the Construction Manager at Risk (CMAR) contract to Hill & Wilkinson General Contractors (19-9024) for pre-construction services in the amount of zero dollars ($0). This award provided for CMAR services including development of project estimates, preliminary construction schedules, value engineering proposals and constructability review during the Design Phase.

Current Change Order/Amendment No. 5 in the amount of $98,214.32 is divided as follows:
$6,755.90 for plumbing work associated with relocation of the Atmos gas meter
$28,244.65 for expanded landscaping within the area just to the east of City Hall West
$29,359.81 for COVID-19 costs associated with monitoring construction workers daily for 3 months
$3,618.76 for painting revisions associated with the exposed ceiling in the entry lobby of City Hall East
$1,960.85 for painting of screening supports along the west wall of City Hall East
$16,927.57 for expanded landscaping to finish the area just south of phase 2 work now versus in phase 3
$4,084.40 for existing door repairs and refinishing at the Transportation Management Center
$8,127.18 for Fire Plan Review storage room revisions and additions
$4,187.75 for additional floor preparation and leveling prior to tile installation due to existing conditions
$34,891.37 for removal/reinstatement of the temporary construction yard on the Boze GPISD property
$4,121.81 for electrical work required to meet code requirements per city ins...

Click here for full text