Legislation Details

File #: 20-10477    Version: 1 Name: Ordinance; Change Order/Amendment No. 8 in the net amount of $10,900 with Axis Contracting, Inc. for Intersection Improvements at three locations (Lone Star Parkway/S. Belt Line Road, Great Southwest Parkway/Lake Ridge Parkway, and Jefferson Street/ South
Type: Ordinance Status: Adopted
File created: 10/16/2020 In control: Engineering
On agenda: 11/3/2020 Final action: 11/3/2020
Title: Ordinance amending the FY 20/21 Capital Improvement Project Budget; Change Order/Amendment No. 8 in the net amount of $10,900 with Axis Contracting, Inc. for Intersection Improvements at three locations (Lone Star Parkway/S. Belt Line Road, Great Southwest Parkway/Lake Ridge Parkway, and Jefferson Street/ South Carrier Parkway intersections)
Attachments: 1. WO 620.70.pdf
From
George Fanous

Title
Ordinance amending the FY 20/21 Capital Improvement Project Budget; Change Order/Amendment No. 8 in the net amount of $10,900 with Axis Contracting, Inc. for Intersection Improvements at three locations (Lone Star Parkway/S. Belt Line Road, Great Southwest Parkway/Lake Ridge Parkway, and Jefferson Street/ South Carrier Parkway intersections)

Presenter
Walter Shumac, Director of Transportation, Gabe Johnson, Director of Public Works and Romin Khavari, City Engineer

Recommended Action
Approve

Analysis
On December 17, 2019 City Council Approved a construction Contract with Axis Contracting, Inc. in the amount of $1,252,354 for Intersection Improvements at three locations; Material testing with Team Consultants in the amount of $28,275; 5% contingency in the amount of $62,618; In-house labor distribution in the amount of $62,618 for a total project cost of $1,405,865.

This project provides for paving, sidewalks, barrier free ramps, traffic signals and drainage improvements at Lone Star Parkway/S. Belt Line Road, Great Southwest Parkway/Lake Ridge Parkway, and Jefferson Street/ South Carrier Parkway intersections.

Proposed Change order/Amendment No. 8 provides for split phasing modifications and lane management during construction at Carrier Parkway/Jefferson Street intersection for a total amount of $10,900; it also provides for smaller batches of concrete and HMAC pavement pours at higher unit costs.

Change order/Amendment No. 7 provided for additional Traffic control and concrete rip rap for PED pole construction at Carrier Parkway/Jefferson Street intersection for a total amount of $3,223.85

Change order/Amendment No. 6 provided for Traffic signal/ PED pole modifications at Carrier Parkway/Jefferson Street intersection for a total amount of $14,116

Change order/Amendment No. 5 in the amount of $5,750 provided for 3” electrical conduit repairs in Carrier Parkway south of Jefferson.

Change order/Amendment No. 4 approv...