Legislation Details

File #: 20-10666    Version: 1 Name: Change Order/Amendment No. 5 with McMahon Contracting, L.P. in the net negative amount of ($7,231.22) for Paving, Drainage and Water Improvements in Ragland Road and Day Miar Road
Type: Agenda Item Status: Consent Agenda
File created: 12/3/2020 In control: Engineering
On agenda: 12/15/2020 Final action: 12/15/2020
Title: Change Order/Amendment No. 5 with McMahon Contracting, L.P. in the net negative amount of ($7,231.22) for Paving, Drainage and Water Improvements in Ragland Road and Day Miar Road
Attachments: 1. 619.76 Ragland.pdf
From
George Fanous

Title
Change Order/Amendment No. 5 with McMahon Contracting, L.P. in the net negative amount of ($7,231.22) for Paving, Drainage and Water Improvements in Ragland Road and Day Miar Road

Presenter
Walter Shumac, Director of Transportation, Gabe Johns, Director of Public Works and Romin Khavari, City Engineer

Recommended Action
Approve

Analysis
On January 7, 2020 City Council approved a construction contract with McMahon Contracting, L.P. in the amount of $3,522,865.43 for Paving, Drainage and Water Improvements in Ragland Road and Day Miar Road; Material Testing with Kleinfelder in the amount of $32,416.55; contract contingency in the amount of $176,143; In-House labor distribution in the amount of $176,143 for a total project cost of $3,907,567.98

Proposed Change order/Amendment No 5 in the net negative amount of ($7,231.22) provides for an increase of 17,725 Square yards of hydro-mulch seeding, 5,330 square yards of erosion control mat and 2” temporary irrigation service line for the entry monument feature; it also provides for a decrease of 4,916 square yards of grass sod. Proposed change order No. 5 has a total increase of $36,275.38 and a total decease of ($43,506.60) for a cumulative amount of $79,781.98 and a net negative amount of ($7,231.22).

Change order/Amendment No 1 in the amount of $ 10,458.94 provided for Waterline adjustment due to a conflict with proposed Storm sewer pipe.

Change order/Amendment No 2 in the net amount of $627.58 provided for pavement and subgrade modifications.

Change order/Amendment No 3 in the net negative amount of ($15,810.26) provided for additional concrete driveway pavement, regrading of ditches, tree removal and quantity modifications of regular and high early strength concrete pavement.

Change order/Amendment No 4 in the net negative amount of ($40,310.47) provided for reducing 25 street light foundations and 670 linear feet of 2” electrical conduits; it also provided for additional 16 ...

Click here for full text