Legislation Details

File #: 17-6695    Version: 1 Name: Ordinance; Change Order/Amendment No. 2 w/SYB Construction for Clean Water State Revoling Fund (CWSRF) Wastewater Rehabilitation project
Type: Ordinance Status: Adopted
File created: 4/21/2017 In control: Engineering
On agenda: 5/2/2017 Final action: 5/2/2017
Title: Ordinance amending the FY 2016/2017 Capital Improvements Projects Budget; Change Order/Amendment No. 2 with SYB Construction in the net amount of $166,791.55 for Clean Water State Revolving Fund (CWSRF) Wastewater Rehabilitation project
Attachments: 1. 17-6695 CWSRF.pdf
From
max

Title
Ordinance amending the FY 2016/2017 Capital Improvements Projects Budget; Change Order/Amendment No. 2 with SYB Construction in the net amount of $166,791.55 for Clean Water State Revolving Fund (CWSRF) Wastewater Rehabilitation project

Presenter
Ron McCuller, Director of Public Works and Romin Khavari, City Engineer

Recommended Action
Approve

Analysis
As part of the City’s ongoing Capital Improvements Program, wastewater locations in decaying condition are recommended for replacement by the Water Utilities staff on a yearly basis. The City contracted with an engineering consultant, RPS Group, to prepare plans and specifications to replace aged wastewater mains in various locations throughout the city with new wastewater mains. For this design package, six (6) locations were identified. On October 11, 2016, the City Council awarded this project to SYB Construction for the low bid amount of $2,604,696.50. Included as part of the contract award was a 5 percent contingency of $130,235.00 for project changes while under construction, which is typical for Capital Improvements projects.

The current Amendment/Change Order No. 2 in the net amount of $166,791.55 provides for a change in the project scope and design for the wastewater line on NE 5th Street between High School Drive and Small Hill Street due to conflicts with existing utilities. The contractor attempted to construct the line as originally designed, but due to unforeseen conflicts with utilities, this location required a re-design to utilize other construction methods in order to alleviate the utility conflicts. This Amendment/Change Order No. 2 also provides for a change in the project scope and design for the wastewater line at the intersection of Corn Valley Rd. and Blueberry Ln. due to conflicts with existing utilities.

Amendment/Change Order No. 1 in the net amount of $177,970.09 provided for the re-construction of a 15-inch wastewater line under Turner Park which was...

Click here for full text