File #: 18-7500    Version: 1 Name: Change Order/Amendment No. 11 with Lee Lewis Construction, Inc. in the amount of $544,124 for Addendum #4 drawing package coordination, water slide structural concrete piers, ductwork rerouting, audio/video (A/V) equipment and lighting at Epic Waters.
Type: Agenda Item Status: Consent Agenda
File created: 12/29/2017 In control: Engineering
On agenda: 1/9/2018 Final action: 1/9/2018
Title: Change Order/Amendment No. 11 with Lee Lewis Construction, Inc. in the amount of $544,124 for Addendum #4 drawing package coordination, water slide structural concrete piers, ductwork rerouting, audio/video (A/V) equipment and lighting at Epic Waters
Attachments: 1. 615.pdf
From
max

Title
Change Order/Amendment No. 11 with Lee Lewis Construction, Inc. in the amount of $544,124 for Addendum #4 drawing package coordination, water slide structural concrete piers, ductwork rerouting, audio/video (A/V) equipment and lighting at Epic Waters

Presenter
Andy Henning, Senior Building and Construction Projects Manager

Recommended Action
Approve

Analysis
On December 9, 2014 the City Council awarded the Construction Manager at Risk (CMAR) contract to Lee Lewis Construction, Inc. for pre-construction services in the amount of $20,000. This award provided the CMAR services including development of project estimates, preliminary construction schedules, value engineering and constructability review during the Design Phase.

The current Change Order/Amendment No. 11 in the amount of $544,124 is divided as follows:
1. $198,386 for Addendum #4 drawing package final coordination consisting of:
a) Electrical revisions (power, theater lighting, motor controls, feeder upsizing)
b) Door and hardware finalization
c) Loading dock traffic coating
2. $294,289 for 34 structural concrete piers for support of the final water slide package
3. $10,591 for ductwork rerouting to improve aesthetics at the main entry corridor of the Epic
4. $35,217 for audio/video (A/V) equipment costs beyond the $1,000,000 allowance carried in the GMP
5. $5,641 for lighting at the Epic Waters cupola structure

Change Order/Amendment No. 1 in the amount of $1,100,000 was approved by City Council on November 3, 2015 (15-5108) allowing for the pre-purchase of aluminum materials that would be utilized in the construction of the OpenAire retractable roof system for the EPIC Waters portion of the project.

Change Order/Amendment No. 2 in the amount of $6,794,652.49 was approved by City Council on February 2, 2016 (16-5323) to get early phase construction activities underway. The elements included in Change Order No. 2 covered the direct subcontract costs for dirt and s...