Legislation Details

File #: 18-7752    Version: 1 Name: Ordinance; Change Order/Amendment No. 2 with McMahon Contracting, Inc. for Palace Parkway, Paving, Drainage, Water & Wastewater Improvements
Type: Ordinance Status: Adopted
File created: 3/23/2018 In control: Engineering
On agenda: 4/3/2018 Final action: 4/3/2018
Title: Ordinance amending the FY 2017/2018 Capital Improvement Project Budget; Change order/ Amendment No.2 with McMahon Contracting in the net total amount of $50,587.50 for Palace Parkway from Belt Line Road to IH-30 Access Road
Attachments: 1. 617.105.pdf, 2. 617.118.pdf, 3. 590.pdf
From
max

Title
Ordinance amending the FY 2017/2018 Capital Improvement Project Budget; Change order/ Amendment No.2 with McMahon Contracting in the net total amount of $50,587.50 for Palace Parkway from Belt Line Road to IH-30 Access Road

Presenter
Gabriel Johnson, Director of Public Works, Walter Shumac, Director of Transportation and Romin Khavari, City Engineer

Recommended Action
Approve

Analysis
On December 12, 2017, City Council approved a construction contract with McMahon Contracting co. in the in the total negotiated amount of $4,616,251.41 for Palace Parkway from Belt Line Road to IH-30 Access Road; Material testing with Reed Engineering in the amount of $86,605; 5% contract contingency in the amount of $230,813; In-house engineering in the amount of $115,406; Street Lighting allowance of $35,000; Signal/Fiber allowance of $40,000 for a total project cost of $5,124,075.41

The Current Change order/ Amendment No.2 provides for the construction of two extra depth wastewater manholes, additional 8” wastewater pipe and other related items of work. This change order was deemed necessary due to unforeseeable challenges related to connections to TRA manhole as well as having to shift the bore pits due to conflicts with buried traffic signal conduit and existing power poles.

Change order/ Amendment No.1 provided for plan revisions related to TRA comments.

State statutes require City Council approval of a change order when the cumulative cost of a change order exceeds $50,000. The cumulative amount of the current amendment/change order No. 2 is $73,440.84 which requires council approval ($62,014.17 increase; $11,426.67 decrease). The amount of C.O #2 is $50,587.50.

Schedule for construction completion date remains October 20, 2018.

Financial Consideration
Funding in the total amount of $50,588 is available as follows:

STRT - $4,976:
1. $4,976 is available in Street Capital Projects Fund (400192) WO #09903603 (Palace Connection to IH-30 off ...