File #: 18-7758    Version: 1 Name: Construction Manager at Risk (CMAR) Contract with Hill & Wilkinson General Contractors for pre-construction services for Phase One of the new City Hall complex and civic campus master plan work
Type: Agenda Item Status: Passed
File created: 3/23/2018 In control: Engineering
On agenda: 4/3/2018 Final action: 4/3/2018
Title: Construction Manager at Risk (CMAR) Contract with Hill & Wilkinson General Contractors for pre-construction services for Phase One of the new City Hall complex and civic campus master plan work in the amount of $5,000 and approve a Construction Services Fee of 2.25% to be applied to the actual approved construction costs for the new City Hall complex and civic campus master plan work at a later time
Attachments: 1. 18-7758 City Hall CMAR.pdf
From
max

Title
Construction Manager at Risk (CMAR) Contract with Hill & Wilkinson General Contractors for pre-construction services for Phase One of the new City Hall complex and civic campus master plan work in the amount of $5,000 and approve a Construction Services Fee of 2.25% to be applied to the actual approved construction costs for the new City Hall complex and civic campus master plan work at a later time

Presenter
Andy Henning, Senior Building and Construction Projects Manager

Recommended Action
Approve

Analysis
On October 17, 2017 the City Council approved an architectural design contract with Rouch Architects (17-7264) for design of renovations and additions to the current City Hall and Development Center in the amount of $1,788,245 along with a 5% contingency in the amount of $89,412 for a total of $1,877,657.

With the design process soon to reach a point of needing important cost estimation and constructability review, an RFP #18054 solicitation was advertised by the City in accordance with State law with respondents to the RFP required to submit their proposals no later than 03/15/2018. Ten Construction Managers responded to the RFP. The selection committee reviewed all of the proposals and ultimately narrowed the field of ten down to a list of four finalists, Steele & Freeman, Pogue Construction, Hill & Wilkinson General Contractors and Crossland Construction, for interview purposes. On 03/21/2018, interviews were conducted with all four firms. After grading of the candidates by the individual committee members and committee deliberations, Hill & Wilkinson General Contractors received the committee’s highest grade and is being recommended to Council for the Pre-Construction CMAR contract award.

While the committee felt it had four outstanding firms to choose from, Hill & Wilkinson's experience in city hall construction and their outstanding team chemistry amongst themselves and with City staff were significant factors weighing in...