Title: Ordinance amending the FY 2016/2017 Capital Improvements Projects Budget; Change Order/Amendment No. 2 with SYB Construction in the net amount of $166,791.55 for Clean Water State Revolving Fund (CWSRF) Wastewater Rehabilitation project
Attachments: 1. 17-6695 CWSRF.pdf

From

max

 

Title

Ordinance amending the FY 2016/2017 Capital Improvements Projects Budget; Change Order/Amendment No. 2 with SYB Construction in the net amount of $166,791.55 for Clean Water State Revolving Fund (CWSRF) Wastewater Rehabilitation project

 

Presenter

Ron McCuller, Director of Public Works and Romin Khavari, City Engineer

 

Recommended Action

Approve

 

Analysis

As part of the City’s ongoing Capital Improvements Program, wastewater locations in decaying condition are recommended for replacement by the Water Utilities staff on a yearly basis.  The City contracted with an engineering consultant, RPS Group, to prepare plans and specifications to replace aged wastewater mains in various locations throughout the city with new wastewater mains.  For this design package, six (6) locations were identified.  On October 11, 2016, the City Council awarded this project to SYB Construction for the low bid amount of $2,604,696.50.  Included as part of the contract award was a 5 percent contingency of $130,235.00 for project changes while under construction, which is typical for Capital Improvements projects. 

 

The current Amendment/Change Order No. 2 in the net amount of $166,791.55 provides for a change in the project scope and design for the wastewater line on NE 5th Street between High School Drive and Small Hill Street due to conflicts with existing utilities.  The contractor attempted to construct the line as originally designed, but due to unforeseen conflicts with utilities, this location required a re-design to utilize other construction methods in order to alleviate the utility conflicts.  This Amendment/Change Order No. 2 also provides for a change in the project scope and design for the wastewater line at the intersection of Corn Valley Rd. and Blueberry Ln. due to conflicts with existing utilities.

 

Amendment/Change Order No. 1 in the net amount of $177,970.09 provided for the re-construction of a 15-inch wastewater line under Turner Park which was not included in the original scope of the construction contract but was deemed in danger of an imminent failure and therefore required an emergency repair.  Amendment/Change Order No. 1 included costs for constructing an 18-inch wastewater line in place of the existing 15-inch wastewater line via pipe bursting, investigation of the existing 15-inch line in Turner Park which was in poor condition, and quantity corrections for pipe rehabilitation and wastewater manholes.

 

City Staff recommends approval of Change Order Number 2.

 

The revised overall project completion date for this construction contract is October 16, 2017.

 

Financial Consideration

Funding in the total amount of $166,792 is available as follows:

 

1. $38,182 is available in Grant (500892) 42513028 (FY14 WWMP-CWSRF) contingency.

2. $128,610 is available by appropriating and transferring from the unobligated fund balance of Water Capital Projects Fund (500592) to Grant (500892) 42513028 (FY14 WWMP-CWSRF).

 

Body

AN ORDINANCE OF THE CITY OF GRAND PRAIRIE, TEXAS, AMENDING THE FY 2016/2017 CAPITAL IMPROVEMENT PROJECTS BUDGET BY TRANSFERRING AND APPROPRIATING $128,610 FROM THE UNOBLIGATED FUND BALANCE IN THE WATER CAPITAL PROJECTS FUND (500592) TO GRANT (500892) 42513028 (FY14 WWMP-CWSRF)

 

NOW, THEREFORE, BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF GRAND PRAIRIE, TEXAS:

 

SECTION 1.  THAT THE FY 2016/2017 Capital Improvement Projects Budget be amended by transferring and appropriating $128,610 from the unobligated fund balance in the Water Capital Projects Fund (500592) to Grant (500892) 42513028 (FY14 WWMP-CWSRF).

 

PASSED AND APPROVED BY THE CITY COUNCIL OF THE CITY OF GRAND PRAIRIE, TEXAS, ON THIS THE 2ND DAY OF MAY, 2017.