File #: 16-6085    Version: 1 Name: Ordinance; Change Order/Amendment No. 5 with SYB for FY 12/13 WWST Replacements
Type: Ordinance Status: Adopted
File created: 9/22/2016 In control: Engineering
On agenda: 10/11/2016 Final action: 10/11/2016
Title: Ordinance amending the FY 2016/2017 Capital Improvements Projects Budget; Change order No. 5 with SYB Construction in the amount of $14,860.00 for wastewater replacements at various locations throughout the City
Attachments: 1. 16-6085 SYB

From

max

 

Title

Ordinance amending the FY 2016/2017 Capital Improvements Projects Budget; Change order No. 5 with SYB Construction in the amount of $14,860.00 for wastewater replacements at various locations throughout the City

 

Presenter

Ron McCuller, Director of Public Works and Romin Khavari, City Engineer

 

Recommended Action

Approve

 

Analysis

On May 19, 2015, the City of Grand Prairie awarded a construction contract to SYB Construction in the amount of $548,527.70 and approved a 5% contingency of $27,426.00 for a total of $575,953.70 for the wastewater replacements construction project. 

 

SYB Construction has now substantially completed work at all six locations included in this construction contract.  Change order/amendment No. 5 in the net amount of $14,860.00 provides for the following:

 

An additional $7,500 for investigation of possible additional sewer services and connections to the City wastewater system at the Dallas St. location.

An additional $9,440 for concrete pavement with asphalt overlay pavement repairs, concrete sidewalk repairs, and hydromulch surface restoration at the W. Main St. location.

A credit of $2,080 dollars for asphalt pavement repairs at the W. Main St. location, as we were unaware at the time of bidding that this pavement was in fact concrete pavement with an asphalt overlay.

 

Change order/amendment No. 1 was in the net amount of $16,879.00 for addition and deletion of items based upon different conditions encountered during the course of construction at the Austrian Way, Graham Street, Dallas Street, NW 23rd Street, and Marshall Drive.

 

Change order/amendment No. 2 was in the net amount of $66,590.00 for additional construction costs due to the re-design and subsequent lowering of the proposed wastewater line because of unforeseen existing utility conflicts encountered during construction at the Marshall Drive/Belt Line Road location.

 

Change order/amendment No. 3 was in the amount of $9,049 for additional work to complete the contract requirements at the NW 23rd/NW 24th Street and Marshall Drive locations. 

 

Change order/amendment No. 4 for a time extension only.

 

The revised overall project completion date for the construction contract is November 30, 2016.

 

Financial Consideration

All project contingency and remaining funds in the work order have been exhausted.

 

Funding is available as follows:

$14,860.00 is available by approving an ordinance transferring and appropriating from the unobligated fund balance in the Wastewater Capital Projects Fund (500692) to WO #01510303 (FY15 Wastewater main Replacements) 68540 (Construction).

 

Body

AN ORDINANCE OF THE CITY OF GRAND PRAIRIE, TEXAS, AMENDING THE FY 2016/2017 CAPITAL IMPROVEMENT PROJECTS BUDGET BY TRANSFERRING AND APPROPRIATING $14,860 FROM THE UNOBLIGATED FUND BALANCE IN THE WASTEWATER CAPITAL PROJECTS FUND (500692) WO #01510303 (FY15 WASTEWATER MAIN REPLACEMENTS)

 

NOW, THEREFORE, BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF GRAND PRAIRIE, TEXAS:

 

SECTION 1.  THAT THE FY 2016/2017 Capital Improvement Projects Budget be amended by transferring and appropriating $14,860 from the unobligated fund balance in the Wastewater Capital Projects Fund (500692) WO #01510303 (FY15 Wastewater Main Replacements)

 

PASSED AND APPROVED BY THE CITY COUNCIL OF THE CITY OF GRAND PRAIRIE, TEXAS, ON THIS THE 11TH DAY OF OCTOBER, 2016.