Ordinance amending the FY 2017/2018 Capital Improvement Projects Budget; Change Order/Amendment No. 2 in the net amount of $333,965.05 with Texas Standard Construction for the Main Street and Jefferson Area Storm Drain Improvements project
Presenter
Romin Khavari, City Engineer
Recommended Action
Approve
Analysis
On January 24, 2017 The City of Grand Prairie awarded a Construction contract with Texas Standard Construction in the amount of $1,817,178.40 for the Main Street and Jefferson Area Storm Drain Improvements project; Material testing with Reed Engineering in the amount of $26,171.00; In-house labor distribution in the amount of $90,859.00; 5% contract contingency in the amount of $90,859.00; for a total project cost of $2,025,067.40
Proposed Change order (Amendment) No.2 provides for various plan revisions and adjustments of the proposed storm drain improvements due to an unknown 42” storm drain that has been determined to extend under the private duplexes north of Dallas street and west under a private grocery store to drain the general area in the net amount of $333,965.05
Staff working closely with the KSA Engineers, the Consulting firm on this project have field determined the exact location of this main as stated above. A design has been provided to re-route this storm drain along existing alleys and east along Dallas Street to connect to the existing storm drain system within dedicated street right-of-ways and easements. Once relocated, the existing storm drain under the duplexes and the grocery store will be filled in and abandoned in place.
Change order (Amendment) No.1 in the amount of $93,220 provided for various plan revisions and adjustments of the proposed storm drain improvements due to several unforeseeable conflicts with existing utilities throughout the construction area. This change order also provides for hand tunneling storm drain pipes.
With approval of the current Change Order/Amendment No. 2, the total amount of all change orders is within the 25% change order total limit of $454,294 for the overall project.
The current Change Order/Amendment No. 2 was approved by the Finance and Government Committee at the November 7th, 2017 meeting for City Council consideration.
Financial Consideration
Funding for the Change Order Amendment No. 2 request in the net amount of $333,966 is available by appropriating and transferring from the un-obligated Storm Capital Projects Fund to (401592) to WO #01405203 (Main St/Jefferson) 68540.
After approval of this change order, the revised total change order amount is within the 25% change order total limit of $454,294 for the overall project.
Body
AN ORDINANCE OF THE CITY OF GRAND PRAIRIE, TEXAS, AMENDING THE FY 2017/2018 CAPITAL IMPROVEMENT PROJECTS BUDGET BY TRANSFERRING AND APPROPRIATING $333,966 FROM THE UNOBLIGATED FUND BALANCE IN THE STORM CAPITAL PROJECTS FUND (401592) WO#01405203 (MAIN ST/JEFFERSON)
NOW, THEREFORE, BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF GRAND PRAIRIE, TEXAS:
SECTION 1. THAT THE FY 2017/2018 Capital Improvement Projects Budget be amended by transferring and appropriating $333,966 from the unobligated fund balance in the Storm Capital Projects Fund (401592) WO#01405203 (Main St/Jefferson)
PASSED AND APPROVED BY THE CITY COUNCIL OF THE CITY OF GRAND PRAIRIE, TEXAS, NOVEMBER 21ST, 2017.