Legislation Details

File #: 19-9574    Version: 1 Name: Change Order No. 2 with SYB Construction Company, Inc for Drainage Improvements 1800 2200 North Carrier Parkway in the in the net amount of $58,786.00.
Type: Agenda Item Status: Consent Agenda
File created: 11/20/2019 In control: Engineering
On agenda: 12/17/2019 Final action: 12/17/2019
Title: Change Order No. 2 with SYB Construction Company, Inc for Drainage Improvements 1800-2200 North Carrier Parkway in the in the net amount of $58,786.00.
Attachments: 1. 619.56.pdf

From

max

 

Title

Change Order No. 2 with SYB Construction Company, Inc for Drainage Improvements 1800-2200 North Carrier Parkway in the in the net amount of $58,786.00.

 

Presenter

Gabe Johnson, Director of Public Works and Romin Khavari, City Engineer

 

Recommended Action

Approve

 

Analysis

On Tuesday, June 18, 2019 the City of Grand Prairie awarded a construction contract to SYB Construction Company, Inc. in the amount of $898,656.84 for Drainage Improvements 1800-2200 North Carrier Parkway.

 

This proposed change order No. 2 will increase the amount of sidewalk replacement authorized in change order #1 by 11 square yards to allow the installation of the box culvert line A, increase the amount of pavement replacement by 325 square yards to provide additional compensation for needed pavement replacement and downsizing the proposed storm drain laterals to clear the discovered GPISD and telemarket company fiber optics lines. This change order includes removal of 16 linear feet of installed 30” Class IV RCP, decrease of contract quantities of 25 linear feet for 3’ by 2’ RCB conduit, of 28 linear feet for 30” Class IV RCP, of 50 linear feet for 30” Class III RCP, of 21 linear feet for 21” Class IV RCP and addition of 50 linear feet of 18” Class III RCP, 47 linear feet of 18” Class IV RCP and 45 linear feet of 12” Class IV RCP for storm drain lateral downsizing to clear the existing fiber optic lines. New items for connections of the downsized storm drain conduits are also provided in this change order.

 

Change order #1 was approved on October 28, 2019 in the amount of $15,097.00 for sidewalk replacement, removal of two large trees, 64 linear foot replacement of the existing 24” Class III RCP for storm drain line E and connection of the storm drain laterals to two existing curb inlets.

 

Construction completion of the project is to be extended to March 24, 2020.

 

Financial Consideration

State statutes require City Council approval of a change order when the cumulative cost of change order exceeds $50,000.  With approval of this change order, the City Manager will be able to approve the change order to a cumulative value of $50,000 without additional Council approval.  Also, the City, as an owner, reserves the right to increase the amount of the work to be performed in a given construction contract by an amount not to exceed twenty-five (25%) percent of the original bid. The amount of the original contract was $898,656.84 and 25% value of this contract is $243,134.96. The Cumulative amount of Change Order #2 is $111,046.00 ($84,916.00 increases and $26,130.00 decreases) which requires council approval. The net amount for Change Order #2 is $58,786.00.

 

Funding in the total amount of $58,786 is available in the Storm Drainage Capital Projects Fund (401592) WO #01905603 (Carrier Parkway Improvements)