Title: Warmack Library Change Order/Amendment No. 3 with Pogue Construction in the amount of $96,838.74 for added structural steel framing, metal stud wall framing adjustments, existing restroom renovations, floor drain provision in mechanical room, entry ramp and vestibule changes, mechanical unit concrete pad adjustments with landscape changes, storm drainage realignment, partition wall allowance reimbursement credit, new acoustical ceiling tile support grid and insulation of piping at restrooms
Attachments: 1. 18-8332 Warmack Library.pdf

From

max

 

Title

Warmack Library Change Order/Amendment No. 3 with Pogue Construction in the amount of $96,838.74 for added structural steel framing, metal stud wall framing adjustments, existing restroom renovations, floor drain provision in mechanical room, entry ramp and vestibule changes, mechanical unit concrete pad adjustments with landscape changes, storm drainage realignment, partition wall allowance reimbursement credit, new acoustical ceiling tile support grid and insulation of piping at restrooms 

 

Presenter

Andy Henning, Senior Building and Construction Projects Manager

 

Recommended Action

Approve

 

Analysis

On August 15, 2017 the City Council awarded the Construction Manager at Risk (CMAR) contract to Pogue Construction for pre-construction services in the amount of $7,500.  This award provided for CMAR services including development of project estimates, preliminary construction schedules, value engineering proposals and constructability review during the Design Phase.

 

The current Change Order/Amendment No. 3 in the amount of $96,838.74 is divided as follows:

$14,732.41 for additional miscellaneous structural steel framing required and masonry brick ledge at the new south programming addition

$1,471.60 for metal stud wall framing adjustments in order to coordinate with code-required structural steel cross bracing

$72,432.35 for complete renovation of the existing restrooms previously not planned for in the overall project scope

$6,826.58 for the addition of a new floor drain in the previously existing concrete slab area where the new mechanical room will be located

$5,482.24 for the addition of a concrete access ramp at the front entry to the facility to supplement the existing ADA ramp currently located to the south of the main entry approach

$1,143.34 for concrete work and landscaping to rotate and hide new mechanical equipment to be located immediately outside existing glazing of the facility

$3,952.92 for storm drain piping adjustments to avoid conflict with structural concrete grade beams

-$18,500 for return of unused portion of privacy screening wall allowance

$7,599.49 for new acoustical ceiling tile grid throughout the library due to demolition impacts

$1,697.81 for code-required insulation of water piping within the chase wall of the restrooms

 

Change Order/Amendment No. 1 in the amount of $4,498,830 was approved by City Council on January 9, 2018 (18-7947) for the Guaranteed Maximum Price (GMP) for the scope of work defined in the Komatsu Architects Construction Documents package as competitively bid by Subcontractors to Pogue Construction.  Costs above and beyond the Pogue Construction portion of the project addressed in the Change Order/Amendment included previously approved construction pre-construction fees ($7,500); previously approved design fees ($434,985); 5% contingency ($208,697); budget allowance for owner-provided FF&E ($450,000); allowance for construction testing ($25,000); allowance for A/V ($25,000); allowance for IT/data ($62,429); allowance for security ($50,000), all of which totaled the overall project budget of $5,762,441.    

 

Change Order/Amendment No. 2 in the amount of $94,388.97 was approved by City Council on August 7, 2018 (18-8073) and was comprised of the following:

$41,778.00 for structural concrete bell pier replacement with steel helical piles in areas where below grade sand pockets were encountered associated with the west adult programming addition

$18,285.91 for Trane HVAC equipment change

$14,173.94 for increased curtain wall depth to meet structural wind loading criteria at all tall glazing locations

$8,695.09 for necessary structural concrete grade beam revisions as required to coordinate with the introduction of the steel helical piles at the west adult programming addition

$1,005.26 for 3 form panel color change associated with designed art installation

$10,450.77 for change from 60 to 70xl solar ban low-e coating for purposes of achieving requirements of the energy code

 

All items will be incorporated into the current Pogue Construction contract for a revised total contract amount of $4,697,557.71

 

This item was taken to the Finance and Government Committee on October 16, 2018 for their review and recommendation for approval.

 

Financial Consideration

Funding in the total amount of $96,838.74 is available in the Library Capital Projects Fund (402093) WO #01701703 (Warmack Expansion Design and Construction) Contract 264864 (Pogue Construction) contingency line 3.