Ordinance amending the FY 2015/2016 Capital Improvement Projects Budget in the amount of $339,725 for a Local Project Advance Funding Agreement (LPAFA) with the Texas Department of Transportation (TxDOT) for the construction of three (3) "Safe Routes to School" sidewalk segments that were submitted and approved for construction under the 2014 Transportation Alternatives Program (TAP) Call for Projects
Presenter
Walter Shumac III, P.E., Director of Transportation Services
Recommended Action
Approve
Analysis
On February 13, 2014, the Regional Transportation Council (RTC) approved approximately $28 million in federal funds for a program called Transportation Alternatives Program (TAP). This funding is to help pay for transportation projects other than building roads. A Call for Projects was issued with a deadline date of May 30, 2014. One of the areas that this funding can be used for is to construct sidewalks designated as “Safe Routes to School”. The Safe Routes to School program identifies and provides sidewalks along the path that children and students could safely use to walk to and from school.
The City of Grand Prairie and the Grand Prairie Independent School District jointly submitted four (4) sidewalk segments in this Call for Projects with The City of Grand Prairie agreeing to be the public sponsor and point of contact for these projects. The Grand Prairie City Council passed resolution #4695-2014 on May 20, 2014 in support of submitting these projects for consideration in the Call for Projects. The three (3) sidewalk segments listed below are moving forward at this time:
1. Matthew Rd. - east side from Alspaugh Ln. to Clark Trl.
2. Crestbrook Ln. - east side from Grenoble Dr. to Stonewall Dr., and
Stonewall Dr. - north side from Crestbrook Ln. to Ferndale Ln.
3. Beatty Dr. - northeast side from Woodacre Dr. to Brian Dr.
These segments of sidewalk were included in this Call for Projects because for various reasons (obstructions, slopes, retaining walls, utilities, etc) they are more expensive to build than a typical sidewalk. Therefore, they have not been built and leave an incomplete path to school.
TxDOT requires a resolution, on a separate agenda item, to be passed in order to enter into a Local Project Advance Funding Agreement (LPAFA).
Financial Consideration
Funding in the amount of $339,725 for the construction, of which 80% will be reimbursed with Federal funds, and 20% will be reimbursed with Transportation Development Credits (TDC), is available by approving an ordinance transferring from the unobligated fund balance in the Street Capital Projects Fund (400192) to Grant Capital Projects Fund (300596) WO# 11516013 (Safe Routes to School Sidewalks) 68540 (Construction).
Body
AN ORDINANCE OF THE CITY OF GRAND PRAIRIE, TEXAS, AMENDING THE FY 2015/2016 CAPITAL IMPROVEMENT PROJECTS BUDGET BY TRANSFERRING AND APPROPRIATING $339,725 FROM THE UNOBLIGATED FUND BALANCE IN THE STREET CAPITAL PROJECTS FUND (400192) TO THE GRANT CAPITAL PROJECTS FUND (300596) WO# 11516013 (SAFE ROUTES TO SCHOOL SIDEWALKS)
NOW, THEREFORE, BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF GRAND PRAIRIE, TEXAS:
SECTION 1. The FY 2015/2016 Capital Improvement Projects Budget be amended by transferring and appropriating $339,725 from the Unobligated Fund balance in the Street Capital Projects Fund (400192) to the Grant Capital Projects Budget (300596) WO# 11516013 (Safe Routes to School Sidewalks).
PASSED AND APPROVED BY THE CITY COUNCIL OF THE CITY OF GRAND PRAIRIE, TEXAS, JUNE 7, 2016.