File #: 17-7364    Version: 1 Name: Ordinance; Construction Contract for Palace Parkway from Belt Line Road to I-30 Access Road
Type: Ordinance Status: Adopted
File created: 11/10/2017 In control: Engineering
On agenda: 12/12/2017 Final action: 12/12/2017
Title: Ordinance amending the FY 2017/2018 Capital Improvement Projects Budget; Construction Contract with McMahon Contracting in the total negotiated amount of $4,616,251.41 for Palace Parkway from Belt Line Road to IH-30 Access Road; Material testing with Reed Engineering in the amount of $86,605; 5% contract contingency in the amount of $230,813; In-house engineering in the amount of $115,406; Street Lighting allowance of $35,000; Signal/Fiber allowance of $40,000 for a total project cost of $5,124,075.41
Attachments: 1. L 2017-11-29 Recommendation.pdf, 2. 590.36.pdf, 3. 617.105.pdf, 4. 617.118.pdf

From

max

 

Title

Ordinance amending the FY 2017/2018 Capital Improvement Projects Budget; Construction Contract with McMahon Contracting in the total negotiated amount of $4,616,251.41 for Palace Parkway from Belt Line Road to IH-30 Access Road; Material testing with Reed Engineering in the amount of $86,605; 5% contract contingency in the amount of $230,813; In-house engineering in the amount of $115,406; Street Lighting allowance of $35,000; Signal/Fiber allowance of $40,000 for a total project cost of $5,124,075.41

 

Presenter

Romin Khavari, City Engineer; Ron McCuller, Director of Public Works; Walter Shumac, Director of Transportation, and Steve Norwood, Director of Planning and Development.

 

Recommended Action

Approve

 

Analysis

Based on Developer interest in this area, and the willingness to dedicated the needed right-of-way and easements for the project, on September 19, 2017, City of Grand Prairie City Council awarded a professional engineering contract to Halff Associates, Inc. to update the 2010 project plans to current standards, including bidding and construction services associated with paving, drainage and utility improvements for Palace Parkway from Beltline Road East to IH-30 Frontage Road. The Right-of-way and easements are currently being finalized for dedication to the City.

 

The project improvements provide for furnishing all labor, material, equipment and performing all work required for the Palace Parkway Paving, Drainage, Water & Wastewater Improvements, consisting of approximately 2,371 feet of linear 4-lane roadway construction, 2,665 linear feet of water line, 2,780 linear feet of wastewater main, construction of a 203-foot 2-barrel 12’x12’ box culvert with headwalls, storm drain pipes, traffic signal adjustments at Belt line Road and other miscellaneous items of work.

 

This project was  bid using the competitive sealed proposal method. On November 14, 2017, the City of Grand Prairie publicly opened eight proposals for this project. All proposers acknowledged receipt of the addenda and submitted bid bonds. Halff Associates, Inc. tabulated the proposals and the results are provided in the table below.

 

On November 27th 2017, the selection Committee met to evaluate the proposals, the Committee's ranking of the proposers is provided below in order:

 

Ranking                                            Proposer                                                                                                                                                   Scoring                                                                                    Original Bid

1                                                                                    McMahon Contracting, L.P.                                          85.79                                                                                                         $4,746,792.81                                          

2                                                                                    Ed Bell                     Construction                                                               82.40                                                                                                         $5,969,664.20

3                                                                                    Jackson Construction                                                               80.09                                                                                                         $4,878,118.65

4                                                                                    RKM Utility Services, Inc.                                          75.33                                                                                                         $4,767,081.70

5                                                                                    Pavecon Public Works                                                               56.19                                                                                                         $4,914,985.65

6                                                                                    Tiseo Paving                                                                                                                              50.89                                                                                                         $5,213,495.10

7                                                                                    Texas Standard Construction                     45.46                                                                                                         $6,246,140.71

8                                                                                    Atkins Brothers Construction                     12.07                                                                                                         $11,328,812.00                                                                                                                                                                                             

 

During the subsequant proposal negotiations with the City, McMahon Contracting agreed to reduce their bid by $130,541.40 to $4,616,251.41. The City also negotiated the number of calendar from the original 300 calendar days to 290 calendar Days.

 

Based on the attached recommendation letter from Halff Associates, Staff is also recommending the award of this construction contract to McMahon Contracting in the final negotiated amount of  $4,616,251.40 and 290 Calendar Days.

 

The Palace Parkway project was presented and approved by the City Council Development Committee on November 20, 2017. The Finance and Government Committee is to consider this item at their December 12th 2017 meeting.

 

Construction of this project is scheduled to start in the first week of January 2018 with projected completion in November 2018.

 

Financial Consideration

$3,876,315 of the funding for this project was included as part of the TIF.

 

Funding in the total amount of $5,124,076 is available as follows:

 

STRT-$4,494,789:

1. $2,655,735 is available in Street Capital Projects Fund (400192) WO #09903603 (Palace Connection to IH-30 off ramp)

2. $1,839,054 is available by transferring and appropriating from the unobligated fund balance in the Street Capital Projects Fund (400192) to WO #09903603 (Palace Connection to IH-30 off ramp)

 

WTER-$281,683:

1. $250,000 is available in Water Capital Projects Fund (500592) WO #01710503 (Palace Parkway WTER)

2. $31,683 is available by transferring and  appropriating from the unobligated fund balance in the Water Capital Projects Fund (500592) to WO #01710503 (Palace Parkway WTER)

 

WWST-$347,604:

1. $260,000 is available in Wastewater Capital Projects Fund (500692) WO#01711803 (Palace Parkway WWST)

2. $87,604 is available by transferring and appropriating from the unobligated fund balance in the Wastewater Capital Projects Fund (500692) to WO #01711803 (Palace Parkway WWST)

 

Body

AN ORDINANCE OF THE CITY OF GRAND PRAIRIE, TEXAS, AMENDING THE CAPITAL IMPROVEMENT PROJECTS BUDGET BY TRANSFERRING AND APPROPRIATING $1,839,054 FROM THE UNOBLIGATED FUND BALANCE IN THE STREET CAPITAL PROJECTS FUND (40019) TO WO #09903603 (PALACE CONNECTION TO IH-30 OFF RAMP) AND $87,604 FROM THE UNOBLIGATED FUND BALANCE IN THE WASTEWATER CAPITAL PROJECTS FUND (500692) TO WO #01711803 (PALACE PARKWAY WWST).

 

NOW, THEREFORE, BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF GRAND PRAIRIE, TEXAS:

 

SECTION 1.  THAT THE FY 2017/2018 Capital Improvement Project Budget be amended by transferring and appropriating $1,839,054 from the unobligated fund balance in the Street Capital Projects Fund (40019) to WO #09903603 (Palace Connection to IH-30 Off Ramp)

 

SECTION 2. THAT THE FY 2017/2018 Capital Improvement Project Budget be amended by transferring and appropriating  $87,604 from the unobligated fund balance in the Wastewater Capital Projects Fund (500692) to WO #01711803 (Palace Parkway WWST)

 

PASSED AND APPROVED BY THE CITY COUNCIL OF THE CITY OF GRAND PRAIRIE, TEXAS, ON THIS THE 12TH DAY OF DECEMBER, 2017.