File #: 18-8178    Version: 1 Name: 2018 Charley Taylor Recreation Center Gym Floor Replacement
Type: Agenda Item Status: Consent Agenda
File created: 8/20/2018 In control: Parks & Recreation
On agenda: 9/4/2018 Final action: 9/4/2018
Title: Contract with Ponder Company Inc. in the amount of $72,030 for removal and replacement of the gym floor at Charley Taylor Recreation Center through the national interlocal agreement with BuyBoard and authorize a 5% contingency in the amount of $3,602 for a total contract amount of $75,632.
Attachments: 1. 18-8178 Charley Taylor Gym Floor.pdf

From

Linda Townley                     

 

Title

Contract with Ponder Company Inc. in the amount of $72,030 for removal and replacement of the gym floor at Charley Taylor Recreation Center through the national interlocal agreement with BuyBoard and authorize a 5% contingency in the amount of $3,602 for a total contract amount of $75,632.

 

Presenter

Rick Herold, Director of Parks, Arts and Recreation

 

Recommended Action

Approve

 

Analysis

On May 2, 2017, the City Council awarded the Construction Manager at Risk (CMAR) contract to Modern Contractors for pre-construction services for the Charley Taylor Recreation Center additions and renovations project in the amount of $1,000.

 

On September 7, 2017, Amendment No 1 for the CMAR in the amount of $4,549,562 representing the Guaranteed Maximum Price (GMP) was approved by the City Council.

 

On October 25, 2017, a purchase order was approved to 1 Priority Environmental Services for asbestos remediation in the meeting rooms, restrooms and gymnasium walls at Charley Taylor Recreation Center.  1 Priority initiated work in mid-December and completed the abatement process on January 17, 2018.  Staff inspected the project site on January 20, 2018 and found significant water damage to the gym floor.  Further investigation revealed the gym floor was a total loss caused by inadequate protection of the floor by the contractor.  The City Attorney's office made contact with TML and made a claim under the City's coverage.  The cost of the gym floor replacement will be covered by the City’s Risk Fund.  TML will seek to recover all costs from the contractor at fault and will reimburse the City’s deductible as part of their subrogation claim.   

 

The City has received a proposal from Ponder Company, Inc. for the removal of the damaged gym floor and sub-floor and replacement, through a cooperative agreement with BuyBoard.  Ponder Company has previously completed work in the City of Grand Prairie as well as for a number of metroplex cities and school districts.  Ponder has submitted a bid in the amount of $72,030.  Staff recommends a 5% contingency in the amount of $3,602 for a total contract amount of $75,632.

 

Chapter 271.102 of the Local Government Code authorizes local governments to participate in a cooperative purchasing program with another local government or local cooperative organization. In lieu of competitive bidding, items and services may be purchased through such agreements as the agreements have already been bid by the sponsoring entity or agency.  The City of Grand Prairie has master inter-local cooperative agreements with various entities including BuyBoard.

 

The BuyBoard is able to save money by pooling the impressive purchasing power of their members, which include hundreds of school districts, municipalities, counties, other local governments, and nonprofits across Texas. They use the power of numbers as leverage to get better prices with the same vendors we use now.

 

This item was presented to the Finance and Government Committee on September 4, 2018 and received recommendation for approval by the City Council.

 

Financial Consideration

Funding is available in the FY 2017/2018 Risk Fund account 212010-64020.