File #: 17-6980    Version: 1 Name: Ordinance; Construction Contract with McMahon Contracting for Drainage Improvements @ Cottonwood Creek Culvert/GSW and Oakdale Road Culvert Improvements
Type: Ordinance Status: Adopted
File created: 7/21/2017 In control: Engineering
On agenda: 8/1/2017 Final action: 8/1/2017
Title: Ordinance amending the FY 2016/2017 Capital Improvement Projects Budget; construction contract with McMahon Contracting, L.P. for Drainage Improvements (#Y1118): Section 1-Cottonwood Creek Culvert Improvements at Great Southwest Parkway Section 2 Oakdale Road Culvert Improvements, in the total amount of $ 1,320,917.08; material testing with Reed Engineering in the amount of $19,802.75; in-house engineering in the amount of $66,045.85; and 5% construction contract contingency in the amount of $66,045.85; for a total project cost of $1,472,811.53
Attachments: 1. 17-6980 Oakdale.pdf, 2. 17-6980 Cottonwood

From

max

 

Title

Ordinance amending the FY 2016/2017 Capital Improvement Projects Budget; construction contract with McMahon Contracting, L.P. for Drainage Improvements (#Y1118): Section 1-Cottonwood Creek Culvert Improvements at Great Southwest Parkway Section 2 Oakdale Road Culvert Improvements, in the total amount of $ 1,320,917.08; material testing with Reed Engineering in the amount of $19,802.75; in-house engineering in the amount of $66,045.85; and 5% construction contract contingency in the amount of $66,045.85; for a total project cost of $1,472,811.53

 

Presenter

Romin Khavari, City Engineer, and Ron McCuller, Director of Public Works

 

Recommended Action

Approve

 

Analysis

On Wednesday, July 12, 2017 the City of Grand Prairie opened bids for Drainage Improvements (#Y1118): Section 1-Cottonwood Creek Culvert Improvements at Great Southwest Parkway, Section 2 Oakdale Road Culvert Improvements. The low bidder is McMahon Contracting, L.P. in the Base Bid amount of $1,320,917.08 for total bid amount of $1,320,917.08.

 

This project was identified as part of the FY17 Capital Projects Budget and Capital Projects Plan for Proposed Storm Drainage Improvements to alleviate flooding. The project consists of two location for Drainage Improvements (#Y1118):

 

Section 1: Cottonwood Creek Culvert Improvements at Great Southwest Parkway.   The drainage improvements at this location  is part of the city wide master drainage plan for the Cottonwood Creek watershed and will provides for 100-year flood culvert improvements along the Great Southwest Parkway crossing at South Fork Cottonwood Creek. This project provides for the construction of two additional 11 foot by 9 foot storm drainage box culvert barrels and inlet upsizing on Great Southwest Parkway to reduce flood backwater upstream of the South Fork Cottonwood Creek crossing. The relocation of an 16 inch water line and 12 inch wastewater line relocations and other miscellaneous items are necessary to complete this project.

 

Section 2: Oakdale Road Culvert Improvements. The drainage improvements at this location will reduce flooding in this area and is intended to keep Beltline Road passable during the high flows. This project provides for the installation of multiple box culvert at three locations along Oakdale Road between SH 161 and Belt Line Road to provide drainage through Oakdale Road between the floodplains of Bear Creek and West Fork Trinity River. The drainage improvements along Oakdale road is comprised of two location with four 4 foot wide by 4 foot high reinforced concrete box culverts, headwalls at each of the two locations, with the third location along Oakdale Road with four 6 foot wide by 3 foot high reinforced concrete box culverts, concrete headwalls and aprons, rock rip rap channel lining,

 

Bids were opened on July 12th for this project and a total of three bids were received:

 

Company                                                                                                                                                                                               Base Bid             Total Bid

McMahon Contracting, L.P.                               $1,320,917.08                                             $1,320,917.08

North Texas Contracting                    $1,433,371.00             $1,433,371.00

Klutz Construction                                                                               $1,491,263.40            $1,491,263.40 

 

Construction of this project is scheduled to begin around the last week of August 2017 with projected completion around June 2018.

 

Financial Consideration

Bids came in substantially higher than the engineer's estimate due to the escalating construction costs:

 

Funding in the total amount of $1,472,812 is as follows:

 

Funding for Cottonwood Creek Culvert Improvements at Great Southwest Parkway (WO #01204601-03) - $765,622:

1. $287,729 is available in Storm Drainage Capital Projects Fund (401592) WO #01204601-03 (Pioneer/GSW Pkwy @ Cottonwood)

2. $477,893 is available by appropriating and transferring from the unobligated fund balance of Storm Drainage Capital Projects Fund (401592) to WO #01204601-03 (Pioneer/GSW Pkwy @ Cottonwood)

 

Funding for Oakdale Road Culvert Improvements (W.O. #613.47) - $707,190:

1. $313,794 is available in Storm Drainage Capital Projects Fund (401592) WO#01304703 (Oakdale Culvert Improvements)

2. $393,396 is is available by appropriating and transferring from the unobligated fund balance of Storm Drainage Capital Projects Fund (401592) to WO #01304703 (Oakdale Culvert Improvements)

 

Body

AN ORDINANCE OF THE CITY OF GRAND PRAIRIE, TEXAS, AMENDING THE FY 2016/2017 CAPITAL IMPROVEMENT PROJECTS BUDGET BY TRANSFERRING AND APPROPRIATING $477,893 FROM THE UNOBLIGATED FUND BALANCE IN THE STORM DRAINAGE CAPITAL PROJECTS FUND (401592) TO WO#01204601-03 (PIONEER/GSW PKWY @ COTTONWOOD) AND $393,396 FROM THE UNOBLIGATED FUND BALANCE IN THE STORM DRAINAGE CAPITAL PROJECTS FUND (401592) WO #01304703 (OAKDALE CULVERT IMPROVMENTS)

 

NOW, THEREFORE, BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF GRAND PRAIRIE, TEXAS:

 

SECTION 1.  THAT THE FY 2016/2017 Capital Improvement Projects Budget be amended by transferring and appropriating $477,893 from the unobligated fund balance in the Storm Drainage Capital Projects Fund (401592) WO #01204601-03 (Pioneer/GSW Pkwy @ Cottonwood)

 

SECTION 2.   THAT THE FY 2016/2017 Capital Improvement Projects Budget by amended by transferring and appropriating $393,396 from the unobligated fund balance in the Storm Drainage Capital Projects Fund (401592) WO #01304703 (Oakdale Culvert Improvements)

 

PASSED AND APPROVED BY THE CITY COUNCIL OF THE CITY OF GRAND PRAIRIE, TEXAS, AUGUST 1ST, 2017.