Legislation Details

File #: 20-10441    Version: 1 Name: Ordinance; Construction contract with Gomez Brothers Construction for Brent Court Storm Drainage Improvements
Type: Ordinance Status: Adopted
File created: 10/2/2020 In control: Engineering
On agenda: 10/13/2020 Final action: 10/13/2020
Title: Ordinance amending the FY 2020/2021 Capital Improvement Projects Budget; Construction contract with Gomez Brothers Construction, Inc. for Brent Court Storm Drainage Improvements in the total amount of $387,046.00; material testing with Team Consultants in the amount of $14,377.80; in-house engineering in the amount of $19,352.30; and 5% construction contract contingency in the amount of $19,352.30 for a total project cost of $440,128.40
Attachments: 1. Brent CT Storm Drain Improvements recommendation for final acceptance 10-01-20.pdf, 2. 20-10441 W.O. 619.58.pdf

From

Max

 

Title

Ordinance amending the FY 2020/2021 Capital Improvement Projects Budget; Construction contract with Gomez Brothers Construction, Inc. for Brent Court Storm Drainage Improvements in the total amount of $387,046.00; material testing with Team Consultants in the amount of $14,377.80; in-house engineering in the amount of $19,352.30; and 5% construction contract contingency in the amount of $19,352.30 for a total project cost of $440,128.40

 

Presenter

Gabe Johnson, Director of Public Works and Romin Khavari, City Engineer

 

Recommended Action

Approve

 

Analysis

On Tuesday, September 29, 2020, the City of Grand Prairie opened bids for Brent Court Storm Drainage Improvements, (W.O. #619.58). The low bidder is Gomez Brothers Construction, Inc. in the total bid amount of $387,046.00.

 

This project was identified as part of the FY19 Capital Projects Budget and Capital Projects Plan for proposed drainage projects. The Brent Court Storm Drainage Improvements, (W.O. #619.58) project provides for underground storm drainage improvements in Marshall Drive at and in Brent Court to address street flooding problems at this location.

 

The Brent Court Storm Drainage Improvements project is part of the City-Wide Master Drainage Plan for storm drainage improvements in the Cottonwood Creek watershed area of the City.

This project provides for installation of 749 linear feet of 30-inch diameter reinforced concrete storm drainage pipe, 259 linear feet of 24-inch diameter reinforced concrete storm drainage pipe, three 20-foot wide street curb drainage inlets in Marshall Drive, replacement of four existing 10-foot wide street curb drainage inlets in Brent Court and Crooks Court, over 910 square yards of asphalt overlaid concrete pavement replacement, replacement of conflicting water and wastewater services and other items necessary for construction as detailed in the plans and specifications.

 

Company                                                                                                                                                                                      Base Bid            Total Bid                                                               

Gomez Brothers Construction, Inc.                                                                                         $387.046.00                                             $387.046.00                       

SYB Construction Company, Inc.                                                                     $ 418,328.00          $ 418,328.00

Jeske Construction Company                                                                                            $427,920.00          $427,920.00

M-Co Construction, Inc.                                                                                                                 $444,504.00                                             $444,504.00

Saber Development Corporation                                                                                        $451,567.00                                             $451,567.00

Atkins Brothers Equipment Co., Inc.                                                                                    $513,539.00                             $513,539.00                     

Canary Construction, Inc.                                                                                                                                  $543,074.00                                             $543,074.00

 

Construction of this project is scheduled to begin around the second week of November 2020 with projected completion around March 2021.

 

Financial Consideration

Funding in the total amount of $440,129 is available as follows:

1. $436,301 is available in Storm Drainage Capital Projects Fund (401592) W.O. 01905803 (Brent Court from West Marshall to Crooks)

2. $3,828 is available by appropriating and transferring from the unobligated fund balance of Storm Drainage Capital Projects Fund (401592) to W.O. 01905803 (Brent Court from West Marshall to Crooks)

 

Body

AN ORDINANCE OF THE CITY OF GRAND PRAIRIE, TEXAS, AMENDING THE FY 2020/2021 CAPITAL IMPROVEMENT PROJECTS BUDGET BY TRANSFERRING AND APPROPRIATING $3,828 FROM THE UNOBLIGATED FUND BALANCE TO W.O. 01905803 (BRENT COURT FROM WEST MARSHALL TO CROOKS)

 

NOW, THEREFORE, BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF GRAND PRAIRIE, TEXAS:

 

SECTION 1. THAT THE FY 2020/2021 Capital Improvement Projects Budget be amended by transferring and appropriating $3,828 from the unobligated fund balance in the FY 2020/2021 Capital Projects Fund to W.O. 01905803 (Brent Court from West Marshall to Crooks)

 

PASSED AND APPROVED BY THE CITY COUNCIL OF THE CITY OF GRAND PRAIRIE, TEXAS, OCTOBER 13, 2020.