File #: 18-8152    Version: 1 Name: Charley Taylor Rec Center Expansion & Renovation CO # 4
Type: Agenda Item Status: Consent Agenda
File created: 8/9/2018 In control: Parks & Recreation
On agenda: 9/4/2018 Final action: 9/4/2018
Title: Change order No. 4 with Modern Contractors in the amount of $19,840.95 for the Charley Taylor Recreation Center Expansion and Renovation Project
Attachments: 1. 18-8152 - CT Recreation Renovations - Capital Projects Budget Summary.pdf

From

Linda Townley

 

Title

Change order No. 4 with Modern Contractors in the amount of $19,840.95 for the Charley Taylor Recreation Center Expansion and Renovation Project

 

Presenter

Rick Herold, Director of Parks, Arts and Recreation

 

Recommended Action

Approve

 

Analysis

On May 2, 2017, the City Council awarded the Construction Manager at Risk (CMAR) contract to Modern Contractors for pre-construction services for the Charley Taylor Recreation Center additions and renovations project in the amount of $1,000.

 

On September 7, 2017, Amendment No 1 for the CMAR in the amount of $4,549,562 representing the Guaranteed Maximum Price (GMP) was approved by the City Council.

 

On March 9, 2018, Change order No. 1 was approved in the additive amount of $13,615.

 

On April 17, 2018, Change order No 2 was approved by City Council in the deductive amount of ($83,038.20) for deletion of HVAC equipment.  Facility Services is coordinating a price agreement contract with Trane for replacement HVAC system with a net savings of $2,773.20.

 

On June 7, 2018, Change order No. 3 was approved in the additive amount of $42,362 and included the following:                     

                     Add adjust to site grading

                     Add structural support at window

                     Add revision to underground utilities

                     Add painting to exterior tile

                     Add revision to interior signage

                     Add steel support for boxing track

                     Delete relocation of water meter

                     Add relocation of FDC per Fire Marshall

                     Additional bike racks

                     Revision of internal locker

                     Add drain pipe guard

The proposed change order #4 in the amount of $19,840.95 would include the following:

                     Revision to boxing bag quantities

                     Add electric circuit to riser room

                     Revision to speed bag brackets

                     Add concrete footing along drainage flume

                     Add electric circuit for motorized partition

                     Add filler to control joint

                     Add demo of plaster ceiling

                     Add roof drain

                     Add relocate RTU frames

                     Add 4” data conduit per City IT

                     Add revisions to concrete roof overhang

 

The cumulative total for change orders to date including this change order exceed the $50,000 threshold for City Manager approval, therefore requires City Council authorization.

 

This item was presented to the Finance and Government Committee on September 4, 2018 and received recommendation for approval by the City Council

 

Financial Consideration

Funding for the Charley Taylor Recreation Center Expansion and Renovation Project is available through the Parks Capital Project Fund (317193) WO #01505501-03 (Charley Taylor Recreation Center Renovations Phase 1).