File #: 10-0697    Version: 1 Name: Change Order with Grantham on Camp Wisdom III
Type: Ordinance Status: Adopted
File created: 11/3/2010 In control: Engineering
On agenda: 11/16/2010 Final action: 11/16/2010
Title: Amendment/Change Order No. 1 with Grantham & Associates, Inc. in the net amount of $17,598.25 for Camp Wisdom Rd III and an ordinance amending the FY2010-2011 CIP budget
Attachments: 1. Fiscal Impact Statement 560.pdf

From

Max

 

Title

Amendment/Change Order No. 1 with Grantham & Associates, Inc. in the net amount of $17,598.25 for Camp Wisdom Rd III and an ordinance amending the FY2010-2011 CIP budget

 

Presenter

Romin Khavari, City Engineer

 

Recommend Action

Approve

 

Analysis

On December 11, 2007, an engineering contract was awarded to Grantham & Associates, Inc. in the amount of $263,471 and authorized a 5% contingency of $13,173 for a total of $276,644 for the design of paving and drainage improvements for Camp Wisdom Road Phase III between Robinson Road and Carrier Parkway.

 

As part of the FY 2011 CIP, the City Council approved shortening this project to only remove the existing dog-leg due to traffic back-up and safety concerns.

 

This Amendment/Change Order No. 1 provides for the preparation of revised engineering plans and specifications for a reduced scope of work.  These revisions include shortening the section of the proposed Camp Wisdom Road between Robinson Road and Carrier Parkway to an approximately 1,000 feet of 4-lane divided roadway to then transition to the existing two lane asphalt roadway.  This proposed section of roadway will straighten Camp Wisdom Road by eliminating the current off-set at Robinson Road and it would enable traffic in Camp Wisdom Road to continue eastward through the Robinson Road signalized intersection towards Carrier Parkway.

 

Financial Consideration

State statutes require City Council approval of a change order when the cumulative cost of this change order exceeds $25,000.  With approval of this change order, the City Manager will be able to approve the change order to a cumulative value of $25,000 without additional Council approval.  Also, the City, as an owner, reserves the right to increase the amount of the work to be performed in a given construction contract by an amount not to exceed twenty-five (25%) percent of the original bid. The amount of this contract is $263,471 and the 25% value of this contract is $65,868.

 

Amendment/Change Order No. 1 request includes deductive items totaling $22,342 and additive items totaling $39,941 resulting in a net change to the contract of $17,599. 

 

Funding in the amount of $17,599 is available as follows:

 

1. $13,173 is available in current contract contingency Street Capital Project Fund (400192 ) WO #06608003 (Camp Wisdom Ph III)

2. $4,426 is available by transferring and appropriating from the unobligated fund balance of the Street Capital Project Fund (400192) to Street Capital Project Fund (400192) WO #06608003 (Camp Wisdom Ph III)

 

Body

AN ORDINANCE OF THE CITY OF GRAND PRAIRIE, TEXAS, AMENDING THE FY 2010/2011CAPITAL IMPROVEMENTS PROJECT BUDGET BY TRANSFERRING AND APPROPRIATING $4,426 FROM THE UNOBLIGATED FUND BALANCE IN THE STREET CAPITAL PROJECTS FUND (400192) TO THE STREET CAPITAL PROJECTS FUND (400192), WO #06608003 (CAMP WISDOM PH III)

 

NOW, THEREFORE, BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF GRAND PRAIRIE, TEXAS:

 

SECTION 1.  THAT THE FY 10/11 Capital Improvements Project Budget be amended by transferring and appropriating $4,426 from the unobligated fund balance in the Street Capital Projects Fund (400192) to the Street Capital Projects Fund (400192) WO #06608003 (Camp Wisdom Ph III)

 

PASSED AND APPROVED BY THE CITY COUNCIL OF THE CITY OF GRAND PRAIRIE, TEXAS, ON THIS THE 16TH DAY OF NOVEMBER, 2010.