File #: 16-5480    Version: 1 Name: CO#1 with Denco for Main Library Remodel
Type: Agenda Item Status: Consent Agenda
File created: 3/8/2016 In control: City Secretary
On agenda: 3/22/2016 Final action: 3/22/2016
Title: Change order number 1 with Denco Construction Specialists in the amount of $68,518.00 for the remodel of the Main Library
Attachments: 1. 16-5480 Denco Change Order #1.pdf, 2. 16-5480 Library Capital Projects Budget Summary

From

Amy Sprinkles

 

Title

Change order number 1 with Denco Construction Specialists in the amount of $68,518.00 for the remodel of the Main Library

 

Presenter

Amy Sprinkles, Marketing/Library Director

 

Recommended Action

Approve

 

Analysis

The Main Library began a major makeover in January 2016.   As we’ve proceeded, several things were not anticipated (soffit detail, exposed structure finishes, isolation valves in restrooms), deconstruction uncovered unseen issues (major mold to remediate, rusted out metal 2x4s and walls to be rebuilt as a result) and some items were not included in the architectural drawings for bid (structural steel for butt glass walls, stairs out back door). 

 

We’ve reached a point of exceeding contingency and are coming back to the City Council to authorize additional funding to cover the work that needs to be done to complete the project:

                     Convert 25 gauge walls to higher gauge per structural engineer

                     Remove VWC from walls

                     Provide stairs out new exterior emergency door in children’s library

                     Reconstruct walls after mold abatement

                     Add structural steel for stacking bay

                     Add exposed structure finishes

                     Soffit demolition and replacement

                     Add isolation valves in all restrooms

                     Fill CMU void in exterior wall cavity

                     Add structural support for ½” butt glass system

                     Relocate VAV from above hard ceiling

                     Reroute roof storm water drain from middle of men’s restroom

                     Change in scope for water wall

 

Money is budgeted in the Capital Budget for $2.3 million renovation in 2016 ($1.1 M for physical renovation; $1 M for furniture and signage; $200,000 for exterior entrance artwork).  The project was approved at by City Council on Nov. 17, 2015, for $768,815, which included a $36,610 contingency and a $732,205 bid.  We are asking for approval for $68,518 (already approved $36,610 contingency plus $31,908.00) to complete items above.  Money is available in the Library’s Main Remodel CIP.

 

Financial Consideration

Funding for the Denco Construction Change Order is available in the Library Capital Projects Fund (402093) WO #01501503 (Main Phase V & VI Remodeling).