Legislation Details

File #: 19-9460    Version: 1 Name: Professional Engineering Services Contract with Teague Nall and Perkins, Inc. for the Fish Creek Bank Stabilization
Type: Agenda Item Status: Consent Agenda
File created: 10/16/2019 In control: Engineering
On agenda: 11/5/2019 Final action: 11/5/2019
Title: Professional Engineering Services Contract with Teague Nall and Perkins, Inc. (TNP) for the design and construction management of the Fish Creek Bank Stabilization Project in the amount of $90,445.00 plus a 5% contingency of $4,522, for a total cost of $94,967
Attachments: 1. 19-9460 620.97 Fish Crk.pdf, 2. 19-9460 620.113 Fish Crk.pdf, 3. FIsh Creek Erosion w & ww lines

From

Stephanie Griffin

 

Title

Professional Engineering Services Contract with Teague Nall and Perkins, Inc. (TNP) for the design and construction management of the Fish Creek Bank Stabilization Project in the amount of $90,445.00 plus a 5% contingency of $4,522, for a total cost of $94,967

Presenter

Gabe Johnson, Director of Public Works and Stephanie Griffin, Floodplain Administrator

 

Recommended Action

Approve

 

Analysis

The City of Grand Prairie has a water line and wastewater line in the vicinity of Fish Creek near the Lake Parks North HOA. This area of Fish Creek has experienced significant erosion in recent years. The City’s infrastructure is at risk. In 2019, the City completed a feasibility alternative solution analysis that recommended gabion basket or modular block wall solution. 

Chapter 252, Section 22 of the Local Government Code allows for the exemption to competitive bidding when the expenditure is for Professional Services such as engineering services. TNP was selected as the most qualified professional due to their familiarity with similar projects in the Metroplex.

 

TNP has provided a proposal to design the bank stabilization solution to protect the City’s infrastructure. The scope of work includes the following tasks:

•                     Task 1: Field Design Survey

•                     Task 2: Environmental & Cultural Resources Coordination

•                     Task 3: Construction Documents

•                     Task 4: Bid/Construction Administration

Financial Consideration

Funding for a Professional Engineering Services Contract with Teague Nall and Perkins, Inc. (TNP) for the design and construction management of the Fish Creek Bank Stabilization Project in the amount of $90,445.00 plus a 5% contingency of $4,522, for a total cost of $94,967 is available as follows:

1. $47,484 is available in the Water Capital Projects Fund (500592) WO #02009703 (Fish Creek Bank Stabilization WTER)

2. $47,483 is available in the Wastewater Capital Projects Fund (500692) WO #02011303 (Fish Creek Bank Stabilization WWST)