File #: 16-6160    Version: 1 Name: c/o 6 w/Lee Lewis Construction for added street and water modifications at Arkansas Lane for the EPIC site
Type: Agenda Item Status: Passed
File created: 10/19/2016 In control: Engineering
On agenda: 11/1/2016 Final action: 11/1/2016
Title: Change Order/Amendment No. 6 with Lee Lewis Construction, Inc. in the amount of $81,269 for the added street and water modifications at Arkansas Lane for the EPIC in Grand Central Park
Attachments: 1. 16-6160 EPIC STRT.pdf, 2. 16-6160 EPIC WTER.pdf

From

max

 

Title

Change Order/Amendment No. 6 with Lee Lewis Construction, Inc. in the amount of $81,269 for the added street and water modifications at Arkansas Lane for the EPIC in Grand Central Park

 

Presenter

Tom Cox, Deputy City Manager

 

Recommended Action

Approve

 

Analysis

On December 9, 2014 the City Council awarded the Construction Manager at Risk (CMAR) contract to Lee Lewis Construction, Inc. for pre-construction services in the amount of $20,000.  This award provided the CMAR services including development of project estimates, preliminary construction schedules, value engineering and constructability review during the Design Phase. 

 

The current Change Order/Amendment No. 6 in the amount of $81,269 is divided as follows: 1. $52,174 is for the added bore at Arkansas Lane and the adjustment at the AT&T conduit lines, Oncor duct bank and re-mobilization. 2. $19,685 for installation of a line stop on the 8" waterline and the cut in of the gate value at the PSB 3. $9,410 for a 13'5" deeper connection on the 16" waterline connection in Arkansas Lane

 

Change Order/Amendment No. 1 in the amount of $1,100,000 was approved by City Council on November 3, 2015 (15-5108) allowing for the pre-purchase of aluminum materials that would be utilized in the construction of the OpenAire retractable roof system for the EPIC Waters portion of the project.

 

Change Order/Amendment No. 2 in the amount of $6,794,652.49 was approved by City Council on March 3, 2016 to get early phase construction activities underway.  The elements included in Change Order No. 2 covered the direct subcontract costs for dirt and site work ($2,217,205.10), underground site utilities installation work ($2,253,997.20), design and fabrication of confirmed water park feature rides to allow for their timely installation ($1,412,117.40), and associated CMAR costs for General Conditions ($650,000) and Insurance and Fees ($261,332.79) for a total approved amount of $6,794,652.49.

 

Change Order/Amendment No. 3 in the amount of $76,067,529 was approved by City Council May 3, 2016 (16-5400) was comprised of three components:  1. $70,142,492 for the balance of the EPIC Water Park construction 2. $650,000 for the walking trail restroom facility, and 3. $5,275,037 for Waterwood/Epic Place previously approved roadway and utilities.

 

Change Order/Amendment No. 4 in the amount of $90,953 was approved by City Council August 2, 2016 (16-5873) was for landscape grading and grubbing for the EPIC PlayGrand Adventures.  Cost savings associated with EPIC Waters will be possible due to EPIC PlayGrand Adventures receiving excavated soil from the basement construction of EPIC Waters versus paying to haul off-site. Funding for the complete EPIC PlayGrand will be from the Sports Corp in the amount of a $2,000,000 one time donation. A resolution on the current council will reimburse the Capital Lending and Reserve Fund after the donation.

 

Change Order/Amendment No. 5 in the amount of $96,178 was approved by City Council October 11, 2016 (16-6134) was for additional material testing with CMJ Engineering, Inc.

 

All items will be incorporated into the current Lee Lewis Construction, Inc. contract for a revised total contract amount of $84,221,487.

 

This item was taken to the Finance and Government Committee on November 1, 2016 for their review and recommendation for approval.

 

Financial Consideration

Funding in the total amount of $81,269 is available as follows:

 

1. $52,174 is available in Street Capital Projects Fund (400192) WO #01610403 (EPIC Way) C15040 contingency

2. $29,095 is available in Water Capital Projects Fund (500592) WO #01607903 (Waterwood Phase I)