File #: 14-4255    Version: 1 Name: EPIC Recreation and Indoor Waterpark
Type: Ordinance Status: Adopted
File created: 11/21/2014 In control: Parks & Recreation
On agenda: 12/9/2014 Final action: 12/9/2014
Title: Ordinance amending the FY 2014/2015 Capital Improvement Projects budget and the Capital Lending and Reserve Fund; and approve a contract with Lee Lewis, Inc., Dallas, Texas in the amount of $20,000 for pre-construction services, and approve a Construction Services Fee of 2% to be applied to the actual approved construction costs for the EPIC Recreation and Indoor Waterpark project and Central Park Improvements
Attachments: 1. 14-4255 The Epic CMAR FIS, 2. 14-4255 The Epic CMAR Fund Amendment
From
Linda Townley
 
Title
Ordinance amending the FY 2014/2015 Capital Improvement Projects budget and the Capital Lending and Reserve Fund; and approve a contract with Lee Lewis, Inc., Dallas, Texas in the amount of $20,000 for pre-construction services, and approve a Construction Services Fee of 2% to be applied to the actual approved construction costs for the EPIC Recreation and Indoor Waterpark project and Central Park Improvements
 
Presenter
Rick Herold
 
Recommended Action
Approve
 
Analysis
In May 2014, citizens approved a referendum for the continuation of a 1/4 cent sales tax for Phase II Improvements to Central Park.  On October 14, 2014, City Council adopted an ordinance appropriating $7,284,660 and approved an architectural services contract with HKS Architects, Dallas, Texas.  
 
On October 14, 2014 proposals were received from six Construction Manager at Risk Contractors at the office of the Purchasing Manager.  The submittals have been evaluated and interviews of the candidates were completed on November 18, 2014.  Based on the submittal package and interviews, staff has unanimously selected Lee Lewis Construction as the finalist to perform Construction Manager at Risk services for the project.  
 
The Construction Manager at Risk services is separated into two components, Pre-Construction; which involves development of project estimates, preliminary construction schedule, value engineering and constructability review during the Design Phase; and Construction Management Services throughout the construction phase of the project.  The Pre-Construction Fee submitted by Lee Lewis Construction is in the amount of $20,000.  
 
Upon completion of the construction plans and contract documents, the project will be advertised for subcontractor bidding.  The CMAR will submit a Guaranteed Maximum Price Amount for the project and Construction Services Fee will be based on the actual approved construction costs in conjunction with the Field & Office Staff and General Conditions fees as outlined below:
 
The Construction Services Fee is based on the following:
1.  Construction Services Percentage:     2% of construction budget       $1,300,000 *
2.  Field & Office Staff Cost:                                                                 $  758,118
3.  General Conditions:                                                                          $1,249,854
 *  2% of estimated $65 million construction cost
 
Based on an estimated $65,000,000 construction contract budget, the total cost of (CMAR services) is $3,327,972 inclusive of both pre-construction ($20,000) and general conditions ($3,307,972).
 
It is anticipated that the design will be completed in approximately one year.  Sub-Contract bids will be received when plans are complete and approved.  The Construction Manager at Risk Contractor will then submit a Guaranteed maximum price proposal for City consideration of award of construction.
 
This proposed ordinance was presented and approved by the Finance and Government Committee on December 9, 2014.
 
Financial Consideration
Funding for a contract with Lee Lewis Construction, Inc., Dallas, Texas in the amount of $20,000 for Pre-Construction Services are available by approving an ordinance transferring and appropriating  from the unobligated fund balance in the Capital Lending and Reserve Fund (402690) to The EPIC Capital Projects Fund (320893), WO #01512001-03 (The EPIC Recreation Center).
 
Body
AN ORDINANCE OF THE CITY OF GRAND PRAIRIE, TEXAS, AMENDING THE FY 2014/2015 CAPITAL IMPROVEMENT PROJECTS BUDGET AND THE CAPITAL LENDING AND RESERVE FUND BY TRANSFERRING AND APPROPRIATING $20,000 FROM THE UNOBLIGATED FUND BALANCE IN THE CAPITAL LENDING RESERVE FUND (402690) TO THE EPIC CAPITAL PROJECTS FUND (320893), WO #01512001-03 (THE EPIC RECREATION CENTER)
 
NOW, THEREFORE, BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF GRAND PRAIRIE, TEXAS:
 
SECTION 1.  THAT the FY 2014/2015 Capital Improvement Projects Budget and the Capital Lending and Reserve Fund be amended by transferring and appropriating $20,000 from the unobligated fund balance in the Capital Lending and Reserve Fund (402690) to the EPIC Capital Projects Fund (320893), WO #01512001-03 (The EPIC Recreation Center)
 
PASSED AND APPROVED BY THE CITY COUNCIL OF THE CITY OF GRAND PRAIRIE, TEXAS, on this the 9th day of december, 2014.