File #: 19-9286    Version: 1 Name: Change Order/Amendment No. 3 with The Home Depot in the amount of $22,030 for structural roof reinforcement, new brick at removed planter area, unforeseen floor preparation required, window replacement, under-slab iron piping removal/replacement, window b
Type: Agenda Item Status: Consent Agenda
File created: 8/23/2019 In control: Engineering
On agenda: 9/3/2019 Final action: 9/3/2019
Title: Change Order/Amendment No. 3 with The Home Depot in the amount of $22,030 for structural roof reinforcement, new brick at removed planter area, unforeseen floor preparation required, window replacement, under-slab iron piping removal/replacement, window blocking/metal trim and built-in buffet counter millwork for the Grand Prairie Historical Building
Attachments: 1. 19-9286 GP Historical.pdf

From

max

 

Title

Change Order/Amendment No. 3 with The Home Depot in the amount of $22,030 for structural roof reinforcement, new brick at removed planter area, unforeseen floor preparation required, window replacement, under-slab iron piping removal/replacement, window blocking/metal trim and built-in buffet counter millwork for the Grand Prairie Historical Building

 

Presenter

Andy Henning, Senior Building and Construction Projects Manager

 

Recommended Action

Approve

 

Analysis

On January 8, 2019 the City Council approved a contract with The Home Depot Hill (19-8554) for complete interior and exterior renovations of the Grand Prairie Historical Building in the amount of $347,246.40.

 

The current Change Order/Amendment No. 3 in the amount of $22,030 is divided as follows:

 

$6,000 - 12” double ply laminated beams to shore up sagging roof structure

$3,110 - removal and replacement of brick associated with the previously existing planter box area

$1,780 - leveling of floor slab at kitchen and conference room areas prior to finish flooring

$500 - replacement of broken window caused by vandalism

$3,000 - replacement of all damaged iron piping under slab in wet area locations

$2,420 - new wood blocking and metal trim wrap for coordination with new window replacement

$5,220 - built-in buffet millwork with storage below in museum area   

 

Change Order/Amendment No. 1 and Change Order/Amendment No. 2 in the total amount of $34,444.44 were approved by the City on June 28, 2019 (Purchase Order 353810) and consisted of exterior stone reinforcement ($28,444.44) and sewer utility upgrades ($6,000).

 

This Change Order/Amendment No. 3 along with the previous Change Order/Amendment No. 1 and Change Order/Amendment No. 2 will be incorporated into the current Home Depot contract for a revised total contract in the amount of $403,720.84

 

This item was taken to the Finance and Government Committee on September 3, 2019 for their review and recommendation for approval.

 

Financial Consideration

Funding for Change Order/Amendment No. 3 with The Home Depot in the amount of $22,030 for structural roof reinforcement, new brick at removed planter area, unforeseen floor preparation required, window replacement, under-slab iron piping removal/replacement, window blocking/metal trim and built-in buffet counter millwork for the Grand Prairie Historical Building, in the total amount of $22,030 is available in the Municipal Facilities Capital Projects Fund (405090) WO #01802101 (Rehab of Historical Organization)