Title: Ordinance amending the FY 2019/2020 Capital Improvement Projects Budget; Change Order/Amendment No. 13 in the net amount of $222,353.82 with Tiseo Paving Company for Great Southwest Parkway Improvements
Attachments: 1. 617.101.pdf, 2. 617.117.pdf, 3. 618.61.pdf, 4. 616.pdf

From

George Fanous

 

Title

Ordinance amending the FY 2019/2020 Capital Improvement Projects Budget; Change Order/Amendment No. 13 in the net amount of $222,353.82 with Tiseo Paving Company for Great Southwest Parkway Improvements

 

Presenter

Romin Khavari, City Engineer; Gabe Johnson, Director of Public Works and Walter Shumac, Director of Transportation.

 

Recommended Action

Approve

 

Analysis

On December 12, 2017 the City of Grand Prairie approved a Construction Contract with Tiseo Paving Company in the total negotiated amount of $12,688,471.60 for Great Southwest Parkway from Sara Jane Parkway to Mayfield Road; materials testing with Alliance Geotechnical Group in the amount of $159,504; 5% contingency in the amount of $634,424; In-house engineering in the amount of $317,212; street lighting allowance of $52,000; signal/fiber allowance of $200,000; additional traffic control allowance by Grand Prairie Police Department $104,000; for a total project cost of $14,155,612

 

This project provides for the construction of approximately 4,900 L.F of 6 concrete lanes divided roadway (89- foot wide) with utilities from IH 20 to Mayfield Road.

 

Proposed Change Order/Amendment No. 13 in the total net amount of $222,353.82 provides for Parkway irrigation along the east side of GSW Parkway between Forum Drive and Sara Jane Parkway which includes three (3) electric irrigation services $44,395.75, Traffic signal modifications at Forum Drive and Sara Jane parkway $29,929.20, and quantity over-runs $134,606.02 related to retaining walls (A thru E), stamped concrete for medians and sidewalks; Sanitary sewer encasement $7,140.00 and $15,806.75 for combination curb inlet and other miscellaneous items of work; it also provides for quantity under-runs ($9,523.90) related to Traffic signal modifications and storm drain inlet adjustments.  This change order provides for a total increase of $231,877.72 and a total decrease of ($9,523.90) for a net amount of $222,353.82

 

Change order/ Amendment No. 1 approved by City Council (18-7833) on May 1, 2018 in the net amount of $19,835 provided for additional 4,100 linear feet of silt fence, 2 additional construction entrances, upsizing 4 wastewater manholes to 5’ manholes and field survey of AT&T lines to determine conflicts.

 

Change Order/Amendment No. 2 approved by City Council (18-8053) on July 17, 2018 in the net amount of $306,783.64.  The change order was required when the contractor found a multi-duct underground AT&T duct system that caused a conflict to construct the TRA 36” main as well as conflicts with the propped bridge piers and storm drain.

 

Change Order/Amendment No. 3 approved by City Council (18-8251) on September 18, 2018 in the net amount of $115,139.15.  The change order was required when a valve on the 24" waterline along Mayfield Road west of Great Southwest Parkway broke and the water main had to be turned off using a line stop to make connection to the new 30" waterline without shutting water off at the water tower and minimally impacting customers. 

 

Change Order/Amendment No.4 administratively approved in the net amount of $2,807.50. The change order was required for additional traffic control at the intersection of Great Southwest Parkway and Sarah Jane.

 

Change Order/Amendment No.5 approved by City Council (18-8367) on November 6, 2018 in the amount of $80,193.05.  The change order was for installing a new 12” line crossing under Great Southwest Parkway that was too shallow, installing steel casing for signal pole bases to prevent water from infiltrating the pole bases and unforeseen damage to repair irrigation and electrical lines for Quality Inn.

 

Change Order/Amendment No.6 approved by City Council (18-8495) on December 11, 2018 in the amount of $44,668.95 The change order was for installing a new 12” line crossing under Great Southwest Parkway that was too shallow, installing steel casing for signal pole bases to prevent water from infiltrating the pole bases and unforeseen damage to repair irrigation and electrical lines for Quality Inn.

 

Change Order/Amendment #7 approved by City Council (19-8548) on January 8, 2019 in the total net amount of $80,329.45 provided for additional driveway replacement, additional depth sanitary sewer manhole, signal wire adjustments and new communication boxes.

 

Change Order/Amendment #8 administratively approved in the amount of $11,100.23 provided for additional subgrade stabilization and hydrated lime for stabilization.

 

Change Order/Amendment #9 administratively approved provided for time extension to the construction contract.

 

Change Order/Amendment #10 administratively approved in the amount of $3,500 provided for a Tree Removal in conflict with construction.

 

Change Order/Amendment #11 administratively approved in the amount of $17,412 provided for demolition of Cross tie retaining wall in conflict with construction including fence removal and replacement.

 

Change Order/Amendment #12 administratively approved in the amount of $12,777.50 provided for a 2” water service and meter box; it also provided for additional concrete rip-rap between the sidewalk and a screening wall. 

 

There are no additional days associated with this change order; thus the completion date is August 2, 2020

 

Financial Consideration

State statute requires City Council approval when the cumulative cost of a change order exceeds $50,000. If approved, the total percentage of change orders from the original contract will be 7.23%.

 

Funding for Change Order/Amendment No. 13 in the net amount of $222,354 with Tiseo Paving Company for Great Southwest Parkway Improvements is available as follows:

 

STRT - $209,544:

 

1. $5,319 is available in Streets Capital Projects Fund (400192), WO #01605703 (GSW Pkwy Sara Jane - STRT) Contract 271430 Contingency Line 2

2. $70,777 is available in Street Capital Projects Fund (400192), WO #01605703 (GSW Pkwy Sara Jane - STRT) Traffic Signals Acct Category (this includes a correction from Change Order/Amendment #7 in the amount of $46,171.45 that was incorrectly charged to the construction contingency instead of the traffic signal allocated budget)

3. $133,448 is available by approving an ordinance transferring and appropriating from the unobligated fund balance in the Street Capital Projects Fund (400192) to WO #01605703 (GSW Pkwy Sara Jane - STRT)

 

WWST - $7,140:

 

4. $7,140 is available by approving an ordinance transferring and appropriating from the unobligated fund balance in the Wastewater Capital Projects Fund (500692) to WO #01711703 (GSW Pkwy Sara Jane - WWST)

 

WTER - $2,520:

 

5. $2,520 is available in Water Capital Projects Fund (500592) WO #01710103 (GSW Pkwy Sara Jane - WTER) Contract 271430 Contingency Line 4

 

STRM - $3,150:

 

6. $3,150 is available in Storm Drainage Capital Projects Fund (401592) WO #01806103 (GSW Pkwy Sara Jane - STRM) Contract 271430 Contingency Line 8

 

Body

AN ORDINANCE OF THE CITY OF GRAND PRAIRIE, TEXAS, AMENDING THE FY 2019/2020 CAPITAL IMPROVEMENT PROJECTS BUDGET BY TRANSFERRING AND APPROPRIATING $133,448 FROM THE UNOBLIGATED FUND BALANCE IN THE STREETS CAPITAL PROJECTS FUND (400192) WO #01605703 (GSW PKWY SARA JANE - STRT) AND $7,140 FROM THE UNOBLIGATED FUND BALANCE IN THE WASTEWATER CAPITAL PROJECTS FUND (500692) TO WO #01711703 (GSW PKWY SARA JANE - WWST)

 

NOW, THEREFORE, BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF GRAND PRAIRIE, TEXAS:

 

SECTION 1.  THAT THEY FY 2019/2020 Capital Improvements Projects Budget be amended by transferring and appropriating $133,448 from the unobligated fund balance in the Street Capital Projects Fund (400192) WO #01605703 (GSW Pkwy Sara Jane - STRT)

 

SECTION 2.  THAT THEY FY 2019/2020 Capital Improvements Projects Budget be amended by transferring and appropriating $7,140 from the unobligated fund balance in the Wastewater Capital Projects Fund (500692) to WO #01711703 (GSW Pkwy Sara Jane - WWST)

 

PASSED AND APPROVED BY THE CITY COUNCIL OF THE CITY OF GRAND PRAIRIE, TEXAS, NOVEMBER 5, 2019.