From
max
Title
Change Order/Amendment No. 12 in the net amount of $153,528.66 with Austin Bridge and Road, L.P. for MacArthur Paving and Drainage Improvements
Presenter
Romin Khavari, City Engineer
Recommended Action
Approve
Analysis
On April 21, 2015 the City of Grand Prairie (15-4571) awarded a construction contract to Austin Bridge and Road, L.P in the bid amount of $14,707,420.34 and a total project cost of $16,205,025 for MacArthur Blvd Paving and Drainage improvements between IH 30 and West fork of the Trinity River.
This project provided for the construction of 4,743 linear feet of 4-lane divided thoroughfare in MacArthur Blvd from IH-30 to north of the West fork of Trinity River to connect to the existing concrete roadway. The project also included the construction of Two-700 linear feet bridges over the Trinity River; 555 linear feet of 37’- wide new concrete roadway to the Land fill Road; construction of approximately 1400 linear feet of bypass channel across the existing Trinity River ox-bow to the west of MacArthur Blvd. to improve channel hydraulics and mitigate for the approximate 4 feet embankment fill required for the roadway.
This proposed Change order/ Amendment No. 12 in the amount of $153,528.66 provides for the construction of approximately 3800 linear feet of 4-foot- sidewalk, 260 feet of 5-foot sidewalk in the TxDot ROW at IH 30 and 40 feet transition section of 10’ sidewalk to tie into the Irving sidewalk north of the bridge to also provide pedestrian access for this area. This change order also provides pedestrian signal at Landfill Road. The sidewalk portion also includes reconstruction of a curb inlet in the TxDot ROW to facilitate a 5 foot sidewalk along the retaining wall.
This change order also provides for replacing the paved median north of the bridge and replacing it with solid sod.
Change order/ Amendment No.1 approved by Council April 5, 2016 (16-5523) in the net negative amount of -$27,431.93 provided for revis...