Ordinance amending the FY 2015/2016 Capital Improvement Projects Budget; construction contract with McMahon Contracting, Inc. in the amount of $1,677,641.72 for Oakdale Paving and Drainage Improvements; 5% construction contingency in the amount of $83,882; material testing with Team Consultants in the amount of $20,910.75; in-house engineering in the amount of $65,428.03; street lighting improvements in the amount of $15,000 for a total project cost of $1,862,862.50
Presenter
Romin Khavari, City Engineer and Ron McCuller, Public Works Director
Recommended Action
Approve
Analysis
This project provides for paving and drainage improvements for Phase I of Oakdale Road between Roy Orr Blvd to the existing dogleg at Old Oakdale Road. Phase I of the Oakdale project consists of 600 feet of concrete 4-lane divided thoroughfare between Roy Orr Blvd and the dogleg at Old Oakdale Rd; it also provides for the installation of traffic signals at the intersection of Oakdale Road and Roy Orr Blvd., storm drain and water main improvements, street lighting and other related items of work.
Phase II segment of Oakdale Road Project provided for 30% design and will extend Oakdale Road 3000 feet eastward to SH 161; design of this segment will be completed and constructed under separate contracts in FY 2021 and beyond and pending future developments in the area.
This project was advertised as competitive sealed proposals method; this method allows the selection of a contractor who provides best value for the City based on pre-established ranking criteria specified in the proposal documents. The City of Grand Prairie received three (3) proposals for this project on Wednesday May 26, 2016 as follows:
Rebcon Total proposal: $2,364,741.27
McMahon Contracting Total proposal: $2,717,302.91
Pavecon Public works, LP. Total proposal: $2,580,322.25
An evaluation committee consisting of City Engineering and Public Works staff and pro...