Ordinance amending the FY 2016/2017 Capital Improvements Projects Budget; Change Order/Amendment No. 2 with Ace Pipe Cleaning, Inc. in the amount of $47,099.20 for wastewater replacements at various locations throughout the city
Presenter
Romin Khavari, City Engineer and Ron McCuller, Director of Public Works.
Recommended Action
Approve
Analysis
On November 3, 2015, the City of Grand Prairie awarded a construction contract to Ace Pipe Cleaning, Inc. in the amount of $753,163.50 and approved a 5% contingency of $37,658.00 for a total of $790,821.50 for the wastewater replacements construction project.
This proposed Change Order/Amendment No. 2 in the net amount of $47,099.20 provides for the installation of a new 8” wastewater main across Tarrant Road by open cut instead of by pipe bursting as noted in the construction plans; additional wastewater line TV inspection and abandonment in place at the Tarrant Road location; shifting buried electrical cables out of the new wastewater line trench at the Tarrant Road location; and additional sod replacement at the Marshall Drive location.
Change Order/Amendment No. 1 was for a time extension only.
The revised overall project completion date for the construction contract is Friday, January 13, 2017.
Financial Consideration
Funding in the total amount of $47,100 is available as follows:
1. $37,658 is available in Wastewater Capital Projects Fund (500692) WO #01510303 (FY15 Wastewater Main Replacements) Contract (C16010) Contingency (Line 2).
2. $9,442 is available by appropriating and transferring from the unobligated fund balance of Wastewater Capital Projects Fund (500692) to WO #01510303 (FY15 Wastewater Main Replacements).