File #: 14-4113    Version: 1 Name: Change Order No.2 with Humphrey & Morton Construction Company, Inc. for Cedar Creek and Prairie Creek Miscellaneous Erosion Project
Type: Agenda Item Status: Consent Agenda
File created: 10/1/2014 In control: Engineering
On agenda: 10/14/2014 Final action: 10/14/2014
Title: Change Order No. 2 with Humphrey & Morton Construction Company, Inc. for Cedar Creek and Prairie Creek miscellaneous erosion project in the net total amount of -$96,425.70
Attachments: 1. C14119 Breakdown, 2. FIS 01208101, 3. FIS 01305003
From
max

Title
Change Order No. 2 with Humphrey & Morton Construction Company, Inc. for Cedar Creek and Prairie Creek miscellaneous erosion project in the net total amount of -$96,425.70

Presenter
Romin Khavari, City Engineer

Recommended Action
Approve

Analysis
On Tuesday, February 18, 2014 the City of Grand Prairie awarded a construction contract to Humphrey & Morton Construction Company, Inc. for Cedar Creek and Prairie Creek Miscellaneous Erosion Project in the total amount of $943,558.80.

This project was identified as part of the FY12 Capital Projects Budget and Capital Projects Plan for Proposed Storm Drainage Projects and provides erosion protection features at four (4) locations along Prairie Creek and ten (10) locations along Cedar Creek to also provide erosion protection at wastewater creek crossings.

The current change order/amendment No. 2 in the total net amount of -$96,425.70 is primarily due to adjustments required due to field conditions for the improvements along the various locations along Prairie and Cedar Creek. During excavation along Cedar Creek Location #8, it was discovered that rock rip rap existed for a large portion of the creek identified for improvements, which resulted in a substantial decrease in work item quantities. Due to field conditions at various locations, adjustments has to be made to add or decrease installation of rock rip-rap and gabions to include adjustments to the capping of existing wastewater main, and other related miscellaneous items of work.

Change order No. 1 in the amount of $37,391.71 was approved by the City on June 9, 2014 to included quantity increases along Prairie Creek. The changes included adjustments to raise a gabion wall due to steep grades, adjustments to a headwall to include repairs due to pipe separation, and grouting of rock rip rap.

The revised contract completion date will be November 20, 2014.

Financial Consideration
Funding in the amount of -$96,425.70 is allocated as...