Change Order #04 for the Dalworth Recreation Center Renovation Construction Manager at Risk contract with Pete Durant and Associates in the amount of $90,052.59 and correct the amount of change order #03 of $103,151.11 to $103,351.11.
Presenter
Rick Herold, Director of Parks, Arts and Recreation
Recommended Action
Approve
Analysis
During the later part of the construction, additional items and repairs have been identified requiring change order approval. Listed below are change orders approved to date and pending change order #04 amount.
Change |
Approved |
|
Order # |
by Council |
Amount |
|
|
|
1 |
|
$1,759.23 |
2 |
11/5/2013 |
$37,257.46 |
3 |
6/3/2014 |
$103,351.11 |
Proposed 4 |
|
$90,052.59 |
Attached is a detailed summary of the modifications included in change order #04.
On June 3, 2014, City Council approved change order #03 which included an error in the amount of the actual change order. The amount of $103,151.11 should be corrected to $103,351.11.
Financial Consideration
Funding for change order #04 in the amount of $90,052.59 is available in the Park Capital Projects Fund (317193), WO #01101903 (Dalworth Expansion).