Skip to main content
File #: 16-6156    Version: 1 Name: Change Order #6 for the AMI project with Itron, Inc for the FY 2016/2017 budget allocation
Type: Agenda Item Status: Consent Agenda
File created: 10/18/2016 In control: Public Works
On agenda: 11/1/2016 Final action: 11/1/2016
Title: Change order #6 for the advanced metering infrastructure project with Itron, Inc.increasing the Itron, Inc. contract by the current year's budget allocation of $2,750,000 for a revised current contract amount of $9,093,597
Attachments: 1. EXHIBIT A.pdf, 2. 16-6156 Itron
From
max

Title
Change order #6 for the advanced metering infrastructure project with Itron, Inc.increasing the Itron, Inc. contract by the current year's budget allocation of $2,750,000 for a revised current contract amount of $9,093,597

Presenter
Ron McCuller, Public Works Director

Recommend Action
Approve

Analysis
On July 14, 2015 City Council awarded a contract to Itron, Inc. for the provision of a fully functioning automated metering infrastructure (AMI) System. The conversion to the new system was to take place over a 5 year period as additional funding is approved by City Council. As part of the FY 2016 budget process additional funds were approved for this project in the amount of $1.25 million.

On November 3, 2015 City Council approved am amendment to the contract with Itron, Inc. for the automated metering infrastructure system in the amount of $1.25 million for year 2 funding of the project and $400,000 for replacement meters as needed. For a total contract amount of $6,900,000, contingent upon future funding approval by the City Council.

Staff requested also to utilize meter replacement funding which is included in the annual operating budgets which will allow for broken meters in the system to be replaced with the AMI technology.

Change orders No. 2-4 were additional items needed for the project that were not included in the original pricing structure. On March 1, 2016, a clarification of the Itron, Inc. contract in the amount of $6,900,000 was presented to the City Council.

As the AMI project progressed, it became apparent that certain areas of the City would be in need of updating existing meter boxes, risers and lids so that the AMI system would be functional for all. The $556,403 will be used for price agreements with Bass & Hays (meter boxes), HD Waterworks (gaskets, riser and bolts) and BlackAnvil (meter bolts) as item 16-5835 on the 7/12/16 City Council agenda.

Change order No. 5 requested $556,403 was released from the cu...

Click here for full text