Title: Final Reconciliation Change Order/Amendment No. 5 with Klutz Construction LLC for Drainage Improvements at various locations in the net amount of $6,559.41
Attachments: 1. 16-5796 Klutz Final

From

max

 

Title

Final Reconciliation Change Order/Amendment No. 5 with Klutz Construction LLC for Drainage Improvements at various locations in the net amount of $6,559.41

 

Presenter

Romin Khavari, City Engineer

 

Recommended Action

Approve

 

Analysis

On March 3, 2015 the City Council of Grand Prairie approved a construction contract to Klutz Construction in the amount of $786,098 for drainage improvements at various locations at two locations: Section I: Outfall rehabilitation along Waterford Drive and Section II: Skyline Road at Henry Branch.

 

Change Order No. 1 approved September 3, 2015 in the amount of $26,521.60 allowed for a TxDOT pedestrian handrail, erosion control blanket, gabion wall, sidewalk and various other items of site restoration.

 

Change Order No. 2 approved October 7, 2015 in the amount of $7,260 allowed for wrought iron fencing in the outfall rehabilitation along Waterford Drive section.

 

Change Order No. 3 and 4 were time extensions only.

 

The current and Final Change Order/Amendment No. 5 provides for final construction adjustments in the net amount of $6,559.41.

 

Total project cost was $829,438.11.

 

Financial Consideration

State statutes require City Council approval of a change order when the cumulative cost of this change order exceeds $50,000.  Additional funding in the amount of $6,559.41 is available in project contingency and in the Stormwater Capital Project Fund (401592) WO #01506201 (FY15 Misc Drainage).