Skip to main content
File #: 18-7526    Version: 1 Name: Change Order/Amendment No. 14 in the net amount of $19,330.55 with Austin Bridge and Road, L.P. for MacArthur Paving and Drainage Improvements
Type: Agenda Item Status: Consent Agenda
File created: 1/12/2018 In control: Engineering
On agenda: 1/23/2018 Final action: 1/23/2018
Title: Change Order/Amendment No. 14 in the net amount of $19,330.55 with Austin Bridge and Road, L.P. for MacArthur Paving and Drainage Improvements
Attachments: 1. 36509015.pdf
From
max

Title
Change Order/Amendment No. 14 in the net amount of $19,330.55 with Austin Bridge and Road, L.P. for MacArthur Paving and Drainage Improvements

Presenter
Romin Khavari, City Engineer

Recommended Action
Approve

Analysis
On April 21, 2015 the City of Grand Prairie (15-4571) awarded a construction contract to Austin Bridge and Road, L.P in the bid amount of $14,707,420.34 and a total project cost of $16,205,025 for MacArthur Blvd Paving and Drainage improvements between IH 30 and West fork of the Trinity River.

This project provided for the construction of 4,743 linear feet of 4-lane divided thoroughfare in MacArthur Blvd from IH-30 to north of the West fork of Trinity River to connect to the existing concrete roadway. The project also included the construction of Two-700 linear feet bridges over the Trinity River; 555 linear feet of 37’- wide new concrete roadway to the Land fill Road; construction of approximately 1400 linear feet of bypass channel across the existing Trinity River ox-bow to the west of MacArthur Blvd. to improve channel hydraulics and mitigate for the approximate 4 feet embankment fill required for the roadway.

This proposed Change order/ Amendment No. 14 in the net amount of $19,330.55 provides for the installation of additional Gabions at the banks of the west fork of the Trinity River, grass sod, Traffic Signal camera and cable and a steel frame gate.

Change order/ Amendment No.1 approved by Council April 5, 2016 (16-5523) in the net negative amount of -$27,431.93 provided for revisions of bridge lighting conduit plans and the addition of an electrical service for bridge lighting on the north side of the Trinity river inside Irving City limits;
Irving will take over Bridge maintenance following completion of construction; change order No.1 also provided for additional storm drain pipe to convey storm water from a low spot area inlet on Forterra plant site and other miscellaneous adjustments.

Change order/ Amendm...