File #: 19-9127    Version: 1 Name: Ordinance; Professional Contract with Freese and Nichols, Inc. for the engineering design of the Sanitary Sewer and electrical Improvements for Loyd Park in the not to exceed amount of $314,845
Type: Ordinance Status: Adopted
File created: 7/5/2019 In control: Engineering
On agenda: 8/6/2019 Final action: 8/6/2019
Title: Ordinance amending the FY 2018/2019 Capital Improvement Projects Budget; Professional Engineering and surveying Contract with Freese and Nichols, Inc. for the engineering design of the Sanitary Sewer and electrical Improvements for Loyd Park in the not to exceed amount of $314,845
Attachments: 1. 19-9127 Loyd Park.pdf
From
max

Title
Ordinance amending the FY 2018/2019 Capital Improvement Projects Budget; Professional Engineering and surveying Contract with Freese and Nichols, Inc. for the engineering design of the Sanitary Sewer and electrical Improvements for Loyd Park in the not to exceed amount of $314,845

Presenter
Duane Strawn, Assistant Parks, Arts and Recreation Director

Recommended Action
Approve

Analysis
On March 3, 2015 the City Council awarded a professional Engineering contract with Freese and Nichols, Inc. (15-4311) for engineering design of adequate roadway, storm drainage, and water and wastewater systems of Ragland Road, Day Miar and Connector roads east of SH 360. As part of this contract, the City approved c/o 1 on August 1, 2016 for providing a wastewater master plan for Loyd Park camp sites.

The current professional Engineering contract with Freese and Nichols, Inc. in the not to exceed amount of $314,845 will include design of the sanitary sewer improvement for Loyd Park loops A, F and G and electrical improvement for loops A, F,G and B.
Upon design completion, Loop B Electrical will bid as added alternate to the construction contract.

A summary of the items included as part of this project:

- Sanitary Sewer Improvements for Loops A, F and G. These improvements include 5200 linear feet of 6" SS and Service connections for all pad sites in these loops as well as appurtenances and pavement repair.

- 30' wide survey of Loops A, F and G

-Electrical system upgrades for Loops A, F, G and Loop B will provide 20A, 30A and 50A, 120V receptacles at each Camp site. The proposed upgrades include replacing the existing transformers and distribution panels serving the campsites in order to accommodate increased load.

-Environmental Coordination will include a pedestrian survey, a technical memorandum documenting finding and a submittal to the Texas Historical Commission as required for a project of this size.

-TRA Coordination of two Point of Entry P...