Change Order/Amendment No.2 with SJ Louis construction for the South Sector Wastewater Gravity Main Project in the total amount of $59,932.00
Presenter
Ron McCuller, Director of Public Works and Romin Khavari, City Engineer
Recommended Action
Approve
Analysis
On February 17, 2015, The City of Grand Prairie awarded a construction contract to S. J. Louis Construction for the South Sector Wastewater Gravity Main Project in the total amount of $4,891,859 and approved a 5% contingency in the amount of $244,593; for a total amount of $5,136,452.
This change order/Amendment No. 2 provides for Extension of 46 linear feet of 48-inch and 11 linear feet of 60-inch steel casing pipe bores across Atmos Energy easements. This quantity increase in boring lengths is in addition to Atmos original agreement with the City’s consulting engineers; the new boring lengths span the entire width of Atmos Energy easements.
Change order No.1 in the net amount of $38,070 for addition of 27 linear feet of 60” steel casing in bore.
Revised project completion date is scheduled for July 16, 2016.
Financial Consideration
Funding for change order #2, in the total amount of $59,932, is available in Wastewater Capital Project Fund (500692) WO #01510003 (South Sector WWST System) 68540 (Construction) Contract C15071 Contingency