Change Order/Amendment No. 1 in the net amount of $8,655.66 with McMahon Contracting, L.P. for Fish Creek Road Paving and Drainage Improvements
Presenter
Romin Khavari, City Engineer
Recommended Action
Approve
Analysis
On November 21, 2017 the City approved a Construction Contract with McMahon Contracting, for Fish Creek Road Paving and Drainage Improvements from Belt Line Road to Dechman/ IH 20 in the amount of $4,134,454.19 and a total project cost of $4,556,728.19.
This Fish Creek Rd project Provided for the construction of approximately 4,800 L.F of 3 concrete lanes (37- foot wide) from Dechman/ IH-20 Service Road to proposed Charter School Road, and for 5 concrete lanes (63-foot wide) from proposed Charter School Road to Belt line Road.
This proposed Change order/ Amendment No. 1 in the net amount $8,655.66 provides for the construction of a 10-inch continuously reinforced concrete TxDot Roadway section at Belt line Road intersection with Fish Creek Rd. it also provides for the adjustments of three water services in conflict with proposed street grade.
Construction completion date remains July 25, 2018.
Financial Consideration
Funding in the total amount of $8,655.66 is available in contract contingency.
1. $5,297.92 is available in Street Capital Projects Fund (400192) WO #01714203 (Fish Creek Alignment - Construction)
2. $3,357.74 is available in Water Capital Projects Fund (500592) WO #01811803 (Fish Creek Rd from Beltline to Westchase Widening/Reconstruction - WTER)