From
Mark Dempsey, Deputy City Attorney
Title
Resolution to deny Oncor's Application to Amend its Distribution Cost Recovery Factor (DCRF) to Increase Distribution Rates
Presenter
Mark Dempsey, Deputy City Manager
Recommended Action
Adopt the resolution denying the Oncor DCRF
Analysis
The City is an electric utility customer of Oncor Electric Delivery Company LLC ("Oncor" or "Company"). The Oncor Cities Steering Committee ("OCSC") is a coalition of similarly situated cities served by Oncor that have joined together to efficiently and cost effectively review and respond to electric issues affecting rates charged in Oncor's service area in matters before the Public Utility Commission ("PUC" or "Commission") and the courts.
On April 3, 2020, Oncor filed an application to Amend its Distribution Cost Recovery Factor ("DCRF") with each of the cities retaining original jurisdiction and with the Commission in Docket No. 50734. In the filing, the Company sought to increase distribution rates by $75.9 million annually (an approximately $0.88 increase to the average residential customer's bill).
The resolution authorizes the City to join with OCSC to evaluate the filing, determine whether the filing complies with law, and if lawful, to determine what further strategy, including settlement, to pursue.
Purpose of Resolution:
The purpose of the Resolution is to deny the DCRF amendment proposed by Oncor.
Explanation of "Be it Ordained" Section:
1. This section authorizes the city to participate with OCSC as a party in the Company's DCRF filing in PUC Docket No. 50734.
2. This section authorizes the hiring of Lloyd Gosselink and consultants to review the filing, negotiate with the Company, and make recommendations to the City regarding reasonable rates. It also authorizes OCSC to direct any necessary administrative proceedings or court litigation associated with an appeal of this application filed with the Commission.
3. This paragraph finds that the Compan...